826 S BURLINGTON AVE 90057

Certificate Information: 826 S BURLINGTON AVE 90057

Application / Permit
24016-10000-35219
Plan Check / Job No.
B24LA30336
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF EXISTING ATTIC IN A HISTORIC SINGLE FAMILY DWELLING BUILT IN 1899 INTO A BEDROOM WITH THE ADDITION OF ONE BATHROOM. INTERIOR WORK ONLY. NO CHANGE TO BUILDING ENVELOPE, BUILDING HEIGHT OR LOT COVERAGE. NO WORK ON THE LOWER FLOORS
Permit Issued
Issued on 5/12/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 KHEDER ALRAZAA
Corrections Issued 11/15/2024 KHEDER ALRAZAA
Quality Review Completed 11/22/2024 KEN GILL
Building Plans Picked Up 11/27/2024 APPLICANT
Applicant returned to address corrections 3/5/2025 KHEDER ALRAZAA
Plan Check Approved 3/27/2025 KHEDER ALRAZAA
Issued 5/12/2025 APPLICANT
CofO in Progress 8/8/2025 WILLIAM SIERRA
Permit Finaled 8/12/2025 DEROLD HAUFF
CofO Issued 8/12/2025 DEROLD HAUFF
Permit Finaled 8/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/13/2025 ADRIAN SANCHEZ
Historic monument Cleared 1/17/2025 LAMBERT GIESSINGER
City Hist. Cultural Monument Cleared 1/24/2025 RAFAEL FONTES
Redevelopment Project Area Cleared 1/28/2025 YASMINE BASHIRI
Eng Process Fee Ord 176,300 Cleared 2/1/2025 ADRIAN SANCHEZ
Sewer availability Cleared 2/1/2025 ADRIAN SANCHEZ

Contact Information

Architect Dunn,, Brooks Marshall; Lic. No.: C32241 2000 ALBERTA AVENUE # 10      VENICE, CA 90291
Contractor Owner-Builder       ,
Engineer Cattan,, Christian George; Lic. No.: C82566 8444 OWENSMOUTH AVE      CANOGA PARK, CA 91304

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/15/2025 Approved FREDDIE RIVERA
Final 5/15/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/15/2025 Approved FREDDIE RIVERA
Green Building Final 5/15/2025 Partial Inspection FREDDIE RIVERA
Green Building Rough 5/15/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/15/2025 Partial Inspection FREDDIE RIVERA
Final 5/21/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 5/21/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/21/2025 Partial Inspection FREDDIE RIVERA
Final 7/9/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved WILLIAM SIERRA
Smoke Detectors 7/9/2025 Approved WILLIAM SIERRA
Final 8/7/2025 OK to Issue CofO WILLIAM SIERRA