460 1/2 N LA JOLLA AVE 90048
Certificate Information: 460 1/2 N LA JOLLA AVE 90048
- Application / Permit
- 24016-10000-35178
- Plan Check / Job No.
- B24LA30272
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Current Status
- CofO Issued on 5/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 11/7/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 1/29/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/14/2025 | ALEC MOUSAKHANIAN |
| Issued | 10/8/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | JOSH MEISTER |
| Permit Finaled | 5/1/2026 | DEROLD HAUFF |
| CofO Issued | 5/1/2026 | DEROLD HAUFF |
| Permit Finaled | 5/1/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2025 | WALLIE JONG |
| Sewer availability | Cleared | 1/7/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 1/22/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/22/2025 | RIDWAN HARDY |
Contact Information
| Architect | Musolino,, John Michael; Lic. No.: NA33574 | , |
| Contractor | Carter Design & Remodeling Inc; Lic. No.: 932102-B | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2025 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 12/12/2025 | Partial Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 12/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/2/2026 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Rough | 1/2/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 1/2/2026 | Approved | JOSH MEISTER |
| Wood Frame | 1/13/2026 | Approved | RAUL BARAJAS |
| Insulation | 1/20/2026 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 1/22/2026 | Approved | JOSH MEISTER |
| Gas Test | 1/22/2026 | Partial Approval | JOSH MEISTER |
| Green Building Rough | 1/22/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/22/2026 | Approved | JOSH MEISTER |
| Underground Mechanical | 1/22/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| Final | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| Green Building Final | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| HVAC-Final | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| METHANE-Final | 3/24/2026 | Approved | JOSH MEISTER |
| METHANE-Rough | 3/24/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Not Ready | JOSH MEISTER |
| Service/Power Release | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| Smoke Detectors | 3/24/2026 | No Access for Inspection | JOSH MEISTER |
| Final | 3/31/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 3/31/2026 | No Access for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Not Ready | JOSH MEISTER |
| Smoke Detectors | 3/31/2026 | No Access for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 4/1/2026 | Approved | JOSH MEISTER |
| Final | 4/1/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 4/1/2026 | Approved | JOSH MEISTER |
| HVAC-Final | 4/1/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 4/1/2026 | Approved | JOSH MEISTER |
| Service/Power Release | 4/1/2026 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/27/2026 | Approved | JOSH MEISTER |
| Final | 4/27/2026 | OK to Issue CofO | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | JOSH MEISTER |
| Smoke Detectors | 4/27/2026 | Approved | JOSH MEISTER |