4951 N SANCOLA AVE 91601

Certificate Information: 4951 N SANCOLA AVE 91601

Application / Permit
24016-10000-35156
Plan Check / Job No.
B24LA30228
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 11/15/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 FERNANDO FLORES
Corrections Issued 11/10/2024 FERNANDO FLORES
Building Plans Picked Up 11/13/2024 APPLICANT
Plan Check Approved 11/14/2024 CRISTINA SALAZAR
Issued 11/15/2024 APPLICANT
CofO in Progress 6/23/2025 JOSE AVILA
Permit Finaled 9/25/2025 RUBEN SALAS
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/12/2024 CARLOS RAMIREZ
Sewer availability Cleared 11/12/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/14/2024 DAVID VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/3/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 2/3/2025 Corrections Issued JOSE AVILA
Wood Frame 2/21/2025 Partial Inspection JOSE AVILA
ELECTRICAL-Rough 3/4/2025 Corrections Issued JOSE AVILA
HVAC-Rough 3/4/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/4/2025 Approved JOSE AVILA
ELECTRICAL-Rough 3/10/2025 Approved JOSE AVILA
Footing/Foundation/Slab 3/10/2025 Approved JOSE AVILA
Wood Frame 3/10/2025 Corrections Issued JOSE AVILA
HVAC-Rough 3/11/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 3/19/2025 Approved JOSE AVILA
Green Building Rough 3/19/2025 Approved JOSE AVILA
Interior/Exterior Lathing 3/19/2025 Approved JOSE AVILA
Drywall Nailing 4/1/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/16/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/27/2025 Not Ready for Inspection JOSE AVILA
HVAC-Final 5/27/2025 Approved JOSE AVILA
ELECTRICAL-Final 6/2/2025 Approved JOSE AVILA
PLUMBING-Final 6/6/2025 Conditional Approval JOSE AVILA
Final 6/12/2025 Corrections Issued JOSE AVILA
Green Building Final 6/12/2025 Approved JOSE AVILA
Smoke Detectors 6/12/2025 Approved JOSE AVILA
Final 6/20/2025 OK to Issue CofO JOSE AVILA