1925 E DARWIN AVE 90031
Certificate Information: 1925 E DARWIN AVE 90031
- Application / Permit
- 24016-10000-35073
- Plan Check / Job No.
- B24LA30161
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- CONVERT (E) GARAGE INTO RECREATION ROOM (360 SF) . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS . "COMPLY WITH DEPARTMENT ORDER effective date 04/23/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" . CEIS Case #805111.
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | SUNMIN LEE |
| Corrections Issued | 11/1/2024 | SUNMIN LEE |
| Plan Check Approved | 1/17/2025 | GEORGE ALVAREZ |
| Issued | 1/17/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/25/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2024 | DAVID LOPEZ |
| Specific Plan | Cleared | 12/9/2024 | ERICK MORALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2025 | Corrections Issued | JACOB SEGURA |
| Pre-Inspection | 5/21/2025 | Corrections Issued | JACOB SEGURA |
| Footing/Foundation/Slab | 6/2/2025 | Partial Approval | JACOB SEGURA |
| Deputy Drilled-In Anchors | 6/10/2025 | Approved | FERMIN RUBIO |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | JACOB SEGURA |
| Footing/Foundation/Slab | 6/11/2025 | Approved | JACOB SEGURA |
| BUILDING-Rough-Frame | 6/30/2025 | Partial Approval | JACOB SEGURA |
| Insulation | 6/30/2025 | Partial Approval | JACOB SEGURA |
| Interior/Exterior Lathing | 6/30/2025 | Partial Approval | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | FERMIN RUBIO |
| BUILDING-Rough-Frame | 7/23/2025 | Corrections Issued | JACOB SEGURA |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Approved | JACOB SEGURA |
| Final | 7/23/2025 | Not Ready for Inspection | JACOB SEGURA |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JACOB SEGURA |
| MERV13>=Final | 7/23/2025 | Approved | JACOB SEGURA |
| MERV13>=Rough | 7/23/2025 | Approved | JACOB SEGURA |
| HVAC-Final | 7/29/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Rough | 7/30/2025 | Approved | JACOB SEGURA |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | JACOB SEGURA |
| Final | 7/31/2025 | Corrections Issued | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV Not Required | JACOB SEGURA |
| Smoke Detectors | 7/31/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Final | 8/6/2025 | Approved | JACOB SEGURA |
| Final | 8/6/2025 | Conditional Approval | JACOB SEGURA |
| HVAC-Final | 8/6/2025 | Approved | JACOB SEGURA |
| PLUMBING-Final | 8/6/2025 | Approved | JACOB SEGURA |