10513 S GORMAN AVE 90002
Certificate Information: 10513 S GORMAN AVE 90002
- Application / Permit
- 24016-10000-34856
- Plan Check / Job No.
- B24LA29886
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert portion of (E) garage w/ addition to detached ADU per Ordinance.
- Permit Issued
- Issued on 10/6/2025
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 4/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | ALEXANDER JOO |
| Corrections Issued | 11/1/2024 | ALEXANDER JOO |
| Building Plans Picked Up | 11/7/2024 | APPLICANT |
| Applicant returned to address corrections | 9/30/2025 | MINA HABILI |
| Plan Check Approved | 10/3/2025 | MINA HABILI |
| Issued | 10/6/2025 | APPLICANT |
| CofO in Progress | 4/23/2026 | ARTHUR NEGRETE |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/14/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 12/16/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/1/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 12/15/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 2/4/2026 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 2/4/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 2/10/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 2/10/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 2/10/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Gas Test | 2/12/2026 | Approved | ARTHUR NEGRETE |
| Shower Pan | 2/12/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 2/24/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/2/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 4/2/2026 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/2/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/7/2026 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 4/7/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/20/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/22/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/22/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 4/22/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/22/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/22/2026 | Approved | ARTHUR NEGRETE |