1853 S STEARNS DR 90035

Certificate Information: 1853 S STEARNS DR 90035

Application / Permit
24016-10000-34734
Plan Check / Job No.
B24LA29698
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert Existing Garage To an ADU PER STATE LAW
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
CofO Issued on 12/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2024 APPLICANT
Assigned to Plan Check Engineer 11/5/2024 NEHEMIAS RAMOS
Corrections Issued 11/6/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 2/3/2025 NGHI SU
Plan Check Approved 2/6/2025 NGHI SU
Issued 2/12/2025 APPLICANT
CofO in Progress 12/19/2025 BRENDAN MORELLI
Permit Finaled 12/19/2025 DEROLD HAUFF
Permit Finaled 12/19/2025 DEROLD HAUFF
CofO Issued 12/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/15/2024 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/15/2024 STEVE MELGAR
Sewer availability Cleared 11/15/2024 STEVE MELGAR
Public Works-Sewers Cleared 11/15/2024 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/19/2024 STEVE MELGAR
Construction within easement Cleared 1/25/2025 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/3/2025 NEHEMIAS RAMOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/18/2025 Partial Inspection ALEX COLIN
PLUMBING-Rough 4/1/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 4/8/2025 Approved ARTHUR NEGRETE
Deputy Drilled-In Anchors 6/6/2025 Conditional Approval ARTHUR NEGRETE
ELECTRICAL-Rough 6/17/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/23/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/23/2025 Approved ARTHUR NEGRETE
Green Building Rough 6/23/2025 Approved ARTHUR NEGRETE
HVAC-Rough 6/23/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/23/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/23/2025 Approved ARTHUR NEGRETE
Insulation 7/8/2025 Not Ready for Inspection ALEX COLIN
Shower Pan 7/8/2025 Approved ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Approved ARTHUR NEGRETE
Insulation 7/10/2025 Approved ARTHUR NEGRETE
Drywall Nailing 7/22/2025 Approved ARTHUR NEGRETE
Sewer 8/6/2025 Approved ARTHUR NEGRETE
Underground Mechanical 8/6/2025 Approved ARTHUR NEGRETE
Final 10/15/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 10/15/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved WILLIAM SIERRA
Smoke Detectors 10/15/2025 Approved WILLIAM SIERRA
Final 12/16/2025 OK to Issue CofO BRENDAN MORELLI
Green Building Final 12/16/2025 Approved BRENDAN MORELLI