17415 W TIARA ST 91316
Certificate Information: 17415 W TIARA ST 91316
- Application / Permit
- 24016-10000-34655
- Plan Check / Job No.
- B24LA29582
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert existing detached Garage into an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Current Status
- CofO Issued on 4/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 11/5/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/27/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 1/13/2025 | JOSEPH RAFOLS |
| Issued | 1/14/2025 | APPLICANT |
| CofO in Progress | 9/2/2025 | MORRIS JACKSON |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
| CofO Issued | 4/25/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/19/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | RYAN CASTRO |
| ZI | Cleared | 12/2/2024 | MAYELA VILLA |
| Construction near power lines | Cleared | 1/10/2025 | GEVORK KARAPETYAN |
Contact Information
| Architect | Maru,, Keyur N; Lic. No.: NA38310 | , |
| Contractor | Caruso'S Construction Inc; Lic. No.: 946650-B | , |
| Contractor | Caruso'S; Lic. No.: 946650-B | , |
| Engineer | Almalla,, Dean; Lic. No.: NA58024 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Partial Approval | MORRIS JACKSON |
| Special/Order Compliance | 3/24/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Corrections Issued | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/22/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 4/22/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 4/22/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 5/1/2025 | Approved | MORRIS JACKSON |
| Wood Frame | 5/1/2025 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | MORRIS JACKSON |
| Insulation | 5/6/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 5/6/2025 | Approved | MORRIS JACKSON |
| Wood Frame | 5/6/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/8/2025 | Approved | MORRIS JACKSON |
| Final | 7/22/2025 | Corrections Issued | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 7/22/2025 | Approved | MORRIS JACKSON |
| Final | 7/25/2025 | OK to Issue CofO | MORRIS JACKSON |