1831 S PONTIUS AVE 90025
Certificate Information: 1831 S PONTIUS AVE 90025
- Application / Permit
- 24016-10000-34630
- Plan Check / Job No.
- B24LA29523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- REMODEL OF (E) WELD SHOP / MANUFACTURING BLDG. INCLUDES REMOVAL OF INTERIOR MEZZANINE, ROOF AND WALL INFILL. (5,694 SF)
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- Issued on 12/5/2024
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/1/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 11/4/2024 | APPLICANT |
| Plan Check Approved | 12/4/2024 | SHANGQIN XIE |
| Issued | 12/5/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Chaney,, Mathew Scott; Lic. No.: C30839 | 1666 ELECTRIC AVENUE VENICE, CA 90291 |
| Contractor | Pinnacle Contracting Corporation; Lic. No.: 665647-B | 21800 BURBANK BLVD #210 WOODLAND HILLS, CA 91367 |
| Engineer | Wilkerson,, Ryan Lee; Lic. No.: S4728 | 20734 SARDINIA WAY PORTER RANCH, CA 91326 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2025 | Partial Inspection | CASIMIR BRITTON |
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 5/15/2025 | Approved | DANIEL VARNUM |
| Drywall Nailing | 5/20/2025 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Reinf. Masonry | 6/23/2025 | Conditional Approval | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Partial Approval | RICARDO ROBLES |
| Masonry Wall/Backfill | 6/24/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Reinf. Masonry | 6/25/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 7/1/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 7/16/2025 | Approved | RICARDO ROBLES |
| Final | 11/14/2025 | Not Ready for Inspection | VASIL MIHALEV |
| METHANE-Final | 11/14/2025 | Not Ready for Inspection | VASIL MIHALEV |
| METHANE-Rough | 11/14/2025 | Approved | VASIL MIHALEV |
| Reinforced Masonry Frame | 11/14/2025 | Not Ready for Inspection | VASIL MIHALEV |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Ready | VASIL MIHALEV |
| Smoke Detectors | 11/14/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Final | 11/26/2025 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Final | 11/26/2025 | Approved | DANIEL VARNUM |
| METHANE-Rough | 11/26/2025 | Approved | DANIEL VARNUM |
| Reinforced Masonry Frame | 11/26/2025 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 11/26/2025 | Approved | DANIEL VARNUM |
| Final | 12/12/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Reinforced Masonry Frame | 12/12/2025 | Approved | RICARDO ROBLES |
| Pre-Inspection | 12/13/2025 | Approved | RICARDO ROBLES |