9320-9322 N VALJEAN AVE 91343
Certificate Information: 9320-9322 N VALJEAN AVE 91343
- Application / Permit
- 24016-10000-34531
- Plan Check / Job No.
- B24LA29385
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO A JADU PER WFPP
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2024 | FERNANDO FLORES |
| Corrections Issued | 10/29/2024 | FERNANDO FLORES |
| Plan Check Approved | 11/15/2024 | MINA HABILI |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 10/7/2025 | RUBEN SALAS |
| Permit Finaled | 10/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/29/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/29/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/13/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 8/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 8/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 8/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 8/26/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/26/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 9/2/2025 | Approved | JENNIFER RABUCHIN |
| Final | 9/26/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/26/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 9/30/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | GAREN HAYRAPETYAN |