6440 N LINDLEY AVE 91335
Certificate Information: 6440 N LINDLEY AVE 91335
- Application / Permit
- 24016-10000-34436
- Plan Check / Job No.
- B24LA29271
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 11/4/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 11/21/2024 | MOHAMMAD ESMAILI |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | JUAN ALVARADO |
| Permit Finaled | 5/27/2025 | JOHN JANSON |
| CofO Issued | 5/27/2025 | JOHN JANSON |
| Permit Finaled | 5/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Built Corp Builders; Lic. No.: 1094354-B | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/11/2024 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/13/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/17/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 2/20/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 2/20/2025 | Partial Approval | JUAN ALVARADO |
| HVAC-Rough | 2/20/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 2/20/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 2/20/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 3/3/2025 | Approved | JUAN ALVARADO |
| Insulation | 3/3/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 3/3/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 3/7/2025 | No Access for Inspection | GEVORK IPCHYAN |
| Final | 4/14/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 4/14/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 4/14/2025 | Approved | ROBERT GOLD |
| Final | 4/24/2025 | Partial Approval | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 4/29/2025 | Approved | JUAN ALVARADO |
| Final | 4/29/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 4/29/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 4/29/2025 | Approved | JUAN ALVARADO |