6440 N LINDLEY AVE 91335

Certificate Information: 6440 N LINDLEY AVE 91335

Application / Permit
24016-10000-34436
Plan Check / Job No.
B24LA29271
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/1/2024 GIOVANNY CHAVEZ
Corrections Issued 11/4/2024 GIOVANNY CHAVEZ
Plan Check Approved 11/21/2024 MOHAMMAD ESMAILI
Issued 11/21/2024 APPLICANT
CofO in Progress 4/30/2025 JUAN ALVARADO
Permit Finaled 5/27/2025 JOHN JANSON
CofO Issued 5/27/2025 JOHN JANSON
Permit Finaled 5/27/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/4/2024 CARLOS AGUILERA
Sewer availability Cleared 11/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/5/2024 CARLOS AGUILERA

Contact Information

Contractor Built Corp Builders; Lic. No.: 1094354-B       ,
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2024 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 12/11/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 12/16/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 12/16/2024 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 1/13/2025 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 1/17/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/20/2025 Partial Approval JUAN ALVARADO
ELECTRICAL-Rough 2/20/2025 Approved JUAN ALVARADO
Green Building Rough 2/20/2025 Partial Approval JUAN ALVARADO
HVAC-Rough 2/20/2025 Approved JUAN ALVARADO
PLUMBING-Rough 2/20/2025 Approved JUAN ALVARADO
Shower Pan 2/20/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 3/3/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Approved JUAN ALVARADO
Green Building Rough 3/3/2025 Approved JUAN ALVARADO
Insulation 3/3/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 3/3/2025 Approved JUAN ALVARADO
Drywall Nailing 3/7/2025 No Access for Inspection GEVORK IPCHYAN
Final 4/14/2025 Corrections Issued ROBERT GOLD
Green Building Final 4/14/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 4/14/2025 Approved ROBERT GOLD
Final 4/24/2025 Partial Approval JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved JUAN ALVARADO
ELECTRICAL-Final 4/29/2025 Approved JUAN ALVARADO
Final 4/29/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 4/29/2025 Approved JUAN ALVARADO
PLUMBING-Final 4/29/2025 Approved JUAN ALVARADO