4121 S MCCLUNG DR 90008

Certificate Information: 4121 S MCCLUNG DR 90008

Application / Permit
24016-10000-34398
Plan Check / Job No.
B24LA29220
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE WITH STORAGE ROOM TO BE CONVERTED TO A DETACHED ADU AND STORAGE ROOM TO REMAIN
Permit Issued
Issued on 12/26/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 CARLOS MONTES
Corrections Issued 11/4/2024 CARLOS MONTES
Building Plans Picked Up 11/6/2024 APPLICANT
Plan Check Approved 12/17/2024 TSE MING HUANG
Issued 12/26/2024 APPLICANT
CofO in Progress 2/27/2026 LUIS CASTRO
Permit Finaled 2/28/2026 DEROLD HAUFF
CofO Issued 2/28/2026 DEROLD HAUFF
Permit Finaled 2/28/2026 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 12/10/2024 MELISSA JONES
Historic monument Cleared 12/10/2024 MELISSA JONES
Address approval Cleared 12/12/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 12/12/2024 DAVID LOPEZ
Sewer availability Cleared 12/12/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/16/2024 WALLIE JONG

Contact Information

Contractor C G S Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/29/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 6/4/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 6/4/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 7/1/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Corrections Issued LUIS CASTRO
Green Building Rough 7/1/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 9/30/2025 Approved LUIS CASTRO
HVAC-Rough 9/30/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 9/30/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 9/30/2025 Approved LUIS CASTRO
Sewer 9/30/2025 Approved LUIS CASTRO
Underground Mechanical 9/30/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 10/22/2025 Corrections Issued LUIS CASTRO
Green Building Rough 10/22/2025 Approved LUIS CASTRO
Insulation 10/22/2025 Not Ready for Inspection LUIS CASTRO
Shower Pan 10/22/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/3/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Approved LUIS CASTRO
Drywall Nailing 11/13/2025 Approved ANTHONY RAMOS
Insulation 11/13/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 11/13/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 2/10/2026 Approved LUIS CASTRO
Final 2/10/2026 Corrections Issued LUIS CASTRO
Green Building Final 2/10/2026 Not Ready for Inspection LUIS CASTRO
HVAC-Final 2/10/2026 Approved LUIS CASTRO
PLUMBING-Final 2/10/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Not Required LUIS CASTRO
Smoke Detectors 2/10/2026 Approved LUIS CASTRO
Final 2/26/2026 OK to Issue CofO LUIS CASTRO
Green Building Final 2/26/2026 Approved LUIS CASTRO