3438 1/2 N DIVISION ST 90065
Certificate Information: 3438 1/2 N DIVISION ST 90065
- Application / Permit
- 24016-10000-34380
- Plan Check / Job No.
- B24LA29194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing detached garage to new ADU with new roof deck.
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Current Status
- Issued on 1/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 11/1/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/23/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/30/2024 | ZAW HAN |
| Plan Check Approved | 1/8/2025 | ZAW HAN |
| Issued | 1/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/12/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2024 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 12/3/2024 | PABLO ESTRADA |
| Grading Pre-Inspection | Cleared | 12/30/2024 | RUSSELL BONVOULOIR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baluyut,, Agustin Pangilinan; Lic. No.: C66025 | 22828 S CYPRESS DR CARSON, CA 90745 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/29/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 7/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/8/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/8/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Wood Frame | 10/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/28/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 10/28/2025 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 10/28/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 12/4/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 12/23/2025 | Approved Pending GreenApproval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |