247 S CITRUS AVE 90036
Certificate Information: 247 S CITRUS AVE 90036
- Application / Permit
- 24016-10000-34218
- Plan Check / Job No.
- B24LA26042
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior renovation of existing single-family residence including new windows and doors at the back-half of the property
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- Current Status
- Issued on 1/27/2025
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | JESSE VIDUYA |
| Corrections Issued | 10/25/2024 | JESSE VIDUYA |
| Quality Review Completed | 10/31/2024 | CHAD DOI |
| Applicant returned to address corrections | 1/3/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 1/14/2025 | JESSE VIDUYA |
| Plan Check Approved | 1/24/2025 | JESSE VIDUYA |
| Plan Check Approved | 1/27/2025 | JESSE VIDUYA |
| Issued | 1/27/2025 | APPLICANT |
Permit Application Clearance Information
| Historic monument | Cleared | 12/4/2024 | LAMBERT GIESSINGER |
| Miscellaneous | Cleared | 12/19/2024 | RUBEN VASQUEZ |
Contact Information
| Architect | Farnham,, Emily; Lic. No.: C34247 | 1621 BAXTER STREET LOS ANGELES, CA 90026 |
| Contractor | Manchen Construction Inc ; Lic. No.: 1043435-B | , |
| Contractor | Manchen Construction Inc; Lic. No.: 1043435-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 3/24/2025 | Partial Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 3/26/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 4/14/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 4/14/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/28/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 4/28/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 4/28/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 4/30/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 4/30/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 4/30/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 5/13/2025 | Conditional Approval | RONNIE MINDANAO |
| HVAC-Rough | 5/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 5/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 5/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 5/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 5/19/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/19/2025 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 5/19/2025 | Corrections Issued | RONNIE MINDANAO |
| Wood Frame | 5/21/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 5/27/2025 | Approved | RONNIE MINDANAO |
| Insulation | 5/27/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 5/27/2025 | Approved | RONNIE MINDANAO |
| Wood Frame | 5/28/2025 | Not Ready for Inspection | JOSH MEISTER |
| Drywall Nailing | 6/3/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 6/3/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/16/2025 | Approved | RONNIE MINDANAO |
| Wood Frame | 6/24/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| Final | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 1/20/2026 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 1/20/2026 | Approved | RONNIE MINDANAO |