6131-6131 3/4 E MONTEREY ROAD 90042
Certificate Information: 6131-6131 3/4 E MONTEREY ROAD 90042
- Application / Permit
- 24016-10000-34119
- Plan Check / Job No.
- B24LA28823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing attached garages to ADU's
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 8/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Zoning Architect | 10/31/2024 | ELAHE MERRIKHI |
| Assigned to Plan Check Engineer | 11/7/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 11/18/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/26/2024 | PRANITA SHAH |
| Plan Check Approved | 2/11/2025 | ARSALAN SHABESTARI |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 8/5/2025 | RONALD JIMENEZ |
| Permit Finaled | 8/6/2025 | RAFAEL ESPINOZA |
| CofO Issued | 8/6/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 8/6/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| ZI | Cleared | 12/4/2024 | YINGSHI HUANG |
| Address approval | Cleared | 12/6/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 12/6/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 12/20/2024 | MICHAEL TEMPLE |
| Green Code | Cleared | 1/9/2025 | MICHAEL AYERS |
| Tenant Habitability Plan | Cleared | 1/13/2025 | RICARDO BOHORQUEZ |
| Zoning Plan Check | Cleared | 1/23/2025 | ELAHE MERRIKHI |
Contact Information
| Contractor | Diversified Build; Lic. No.: 1033675-B | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 3/19/2025 | Approved | RAMAZANALI ALMASI |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | JEROME BLACKWOOD |
| Green Building Rough | 4/21/2025 | Approved | JEROME BLACKWOOD |
| Wood Frame | 4/21/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 4/25/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 4/25/2025 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 4/30/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 4/30/2025 | Approved | RONALD JIMENEZ |
| Final | 7/23/2025 | Conditional Approval | RONALD JIMENEZ |
| Green Building Final | 7/23/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 7/23/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 7/23/2025 | Approved | RONALD JIMENEZ |
| Final | 7/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 8/5/2025 | OK to Issue CofO | RONALD JIMENEZ |