1471 1/2 E 22ND ST 90011
Certificate Information: 1471 1/2 E 22ND ST 90011
- Application / Permit
- 24016-10000-34112
- Plan Check / Job No.
- B24LA28807
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO DETACHED ADU PER GCS 65852.2(e) (1)(A). NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 3/3/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | ADAM HEGAZI |
| Corrections Issued | 11/5/2024 | ADAM HEGAZI |
| Building Plans Picked Up | 11/7/2024 | APPLICANT |
| Plan Check Approved | 12/19/2024 | CRISTINA SALAZAR |
| Issued | 3/3/2025 | APPLICANT |
| CofO in Progress | 8/6/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
| CofO Issued | 8/9/2025 | DEROLD HAUFF |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 11/13/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/3/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 4/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/1/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/5/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 7/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 7/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/5/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/5/2025 | Approved | ALEJANDRO DE ARTOLA |