1471 1/2 E 22ND ST 90011

Certificate Information: 1471 1/2 E 22ND ST 90011

Application / Permit
24016-10000-34112
Plan Check / Job No.
B24LA28807
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO DETACHED ADU PER GCS 65852.2(e) (1)(A). NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 3/3/2025
Issuing Office
Metro
Current Status
CofO Issued on 8/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 ADAM HEGAZI
Corrections Issued 11/5/2024 ADAM HEGAZI
Building Plans Picked Up 11/7/2024 APPLICANT
Plan Check Approved 12/19/2024 CRISTINA SALAZAR
Issued 3/3/2025 APPLICANT
CofO in Progress 8/6/2025 ALEJANDRO DE ARTOLA
Permit Finaled 8/9/2025 DEROLD HAUFF
CofO Issued 8/9/2025 DEROLD HAUFF
Permit Finaled 8/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/13/2024 JUSTIN BICOL
Sewer availability Cleared 11/13/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/16/2024 JUSTIN BICOL

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/5/2025 Approved ALEJANDRO DE ARTOLA
Sewer 3/5/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/5/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/3/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 4/3/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/4/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/17/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 4/17/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/17/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/17/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/17/2025 Approved ALEJANDRO DE ARTOLA
Insulation 4/23/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/1/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 6/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/5/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 7/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 7/21/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/22/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/22/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/23/2025 Approved ALEJANDRO DE ARTOLA
Final 7/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/23/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/23/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/24/2025 Approved ALEJANDRO DE ARTOLA
Final 7/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 7/24/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/5/2025 Approved ALEJANDRO DE ARTOLA
Final 8/5/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 8/5/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/5/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/5/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/5/2025 Approved ALEJANDRO DE ARTOLA