4960 1/2 W AMBROSE AVE 90027

Certificate Information: 4960 1/2 W AMBROSE AVE 90027

Application / Permit
24016-10000-33999
Plan Check / Job No.
B24LA28621
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Detached Garage to (N) Accessory Dwelling Unit with addition per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
Permit Issued
Issued on 7/2/2025
Issuing Office
Current Status
CofO Issued on 3/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2024 APPLICANT
Assigned to Plan Check Engineer 10/29/2024 AMY GUEVARRA
Corrections Issued 11/1/2024 AMY GUEVARRA
Applicant returned to address corrections 4/15/2025 AMY GUEVARRA
Plan Check Approved 5/9/2025 CAROLEAN BASMA
Issued 7/2/2025 APPLICANT
CofO in Progress 3/26/2026 ENRIQUE MIRELES
Permit Finaled 3/28/2026 DEROLD HAUFF
CofO Issued 3/28/2026 DEROLD HAUFF
Permit Finaled 3/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/21/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 11/21/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/3/2024 WALLIE JONG
Sewer availability Cleared 12/3/2024 WALLIE JONG
Grading Pre-Inspection Cleared 12/4/2024 MICHAEL TEMPLE
Construction near power lines Cleared 3/11/2025 ENRIQUE ACOSTA
Miscellaneous Cleared 4/22/2025 ALBERT TAM

Contact Information

Contractor Blue Pacific Contractors Inc; Lic. No.: 1022139-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: NA93095       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2025 Not Ready for Inspection JOSH MEISTER
Deputy Drilled-In Anchors 7/15/2025 Approved ENRIQUE MIRELES
Underground Mechanical 7/15/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Approved ENRIQUE MIRELES
Green Building Rough 8/5/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/20/2025 Approved ENRIQUE MIRELES
HVAC-Rough 8/20/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/20/2025 Approved ENRIQUE MIRELES
Shower Pan 8/20/2025 Approved ENRIQUE MIRELES
Insulation 8/26/2025 Not Ready for Inspection ALEX COLIN
Interior/Exterior Lathing 8/26/2025 Approved ALEX COLIN
Insulation 8/27/2025 Approved ENRIQUE MIRELES
Drywall Nailing 9/11/2025 Conditional Approval JOSH MEISTER
Underground Mechanical 9/11/2025 Partial Approval JOSH MEISTER
Green Building Rough 9/24/2025 Approved ENRIQUE MIRELES
Underground Mechanical 9/24/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/2/2026 Approved ENRIQUE MIRELES
Final 2/2/2026 Corrections Issued ENRIQUE MIRELES
Green Building Final 2/2/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/2/2026 Approved ENRIQUE MIRELES
Final 3/11/2026 OK to Issue CofO ENRIQUE MIRELES