4122 N BELLINGHAM AVE 91604
Certificate Information: 4122 N BELLINGHAM AVE 91604
- Application / Permit
- 24016-10000-33914
- Plan Check / Job No.
- B24LA28516
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND (E) REC ROOM TO (N) ADU COMPLY WITH DEPARTMENT ORDER effective date 08/30/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | FERNANDO FLORES |
| Corrections Issued | 10/27/2024 | FERNANDO FLORES |
| Building Plans Picked Up | 10/31/2024 | APPLICANT |
| Applicant returned to address corrections | 8/11/2025 | CARLOS MONTES |
| Plan Check Approved | 8/18/2025 | DANIEL YIP |
| Issued | 8/19/2025 | APPLICANT |
| CofO in Progress | 1/26/2026 | PTOLEMY HILL |
| Permit Finaled | 2/19/2026 | DANIEL SANCHEZ |
| CofO Issued | 2/19/2026 | DANIEL SANCHEZ |
| Permit Finaled | 2/19/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/15/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 11/20/2024 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 1/22/2025 | GEVORK KARAPETYAN |
Contact Information
| Engineer | Franceschi,, Paul; Lic. No.: S4309 | 2388 KENILWORTH AVE LOS ANGELES, CA 90039 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2025 | Approved | PTOLEMY HILL |
| Excavation/Setback/Form/Re-Bar | 11/6/2025 | Approved | PTOLEMY HILL |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | PTOLEMY HILL |
| ELECTRICAL-Rough | 12/2/2025 | Approved | PTOLEMY HILL |
| Green Building Rough | 12/2/2025 | Approved | PTOLEMY HILL |
| HVAC-Rough | 12/2/2025 | Approved | PTOLEMY HILL |
| PLUMBING-Rough | 12/2/2025 | Approved | PTOLEMY HILL |
| Insulation | 12/5/2025 | Approved | JONATHAN FRANCHINI |
| Interior/Exterior Lathing | 12/5/2025 | Approved | JONATHAN FRANCHINI |
| Drywall Nailing | 12/12/2025 | Approved | JONATHAN FRANCHINI |
| Underground Mechanical | 12/12/2025 | Approved | JONATHAN FRANCHINI |
| ELECTRICAL-Final | 1/23/2026 | Approved | PTOLEMY HILL |
| Final | 1/23/2026 | OK to Issue CofO | PTOLEMY HILL |
| Green Building Final | 1/23/2026 | Approved | PTOLEMY HILL |
| HVAC-Final | 1/23/2026 | Approved | PTOLEMY HILL |
| PLUMBING-Final | 1/23/2026 | Approved | PTOLEMY HILL |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | PTOLEMY HILL |
| Smoke Detectors | 1/23/2026 | Approved | PTOLEMY HILL |