6122 W DEL VALLE DR 90048
Certificate Information: 6122 W DEL VALLE DR 90048
- Application / Permit
- 24016-10000-33835
- Plan Check / Job No.
- B24LA28429
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER STATE LAW
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2024 | SHANGQIN XIE |
| Corrections Issued | 10/25/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/6/2024 | TSE MING HUANG |
| Applicant returned to address corrections | 4/11/2025 | TSE MING HUANG |
| Plan Check Approved | 4/16/2025 | TSE MING HUANG |
| Issued | 8/12/2025 | APPLICANT |
| CofO in Progress | 6/10/2026 | SCOTT FINNILA |
| Permit Finaled | 6/11/2026 | DEROLD HAUFF |
| CofO Issued | 6/11/2026 | DEROLD HAUFF |
| Permit Finaled | 6/11/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/20/2024 | ADRIAN SANCHEZ |
| City Hist. Cultural Monument | Cleared | 4/15/2025 | DEBORAH MCGILL |
| HPOZ | Cleared | 4/15/2025 | DEBORAH MCGILL |
| Historic monument | Cleared | 4/15/2025 | DEBORAH MCGILL |
Contact Information
| Architect | Jenny,, Cody; Lic. No.: C41469 | 750 GARLAND AVENUE #436 LOS ANGELES, CA 90017 |
| Contractor | Kink Construction; Lic. No.: 1069598-B | , |
| Engineer | Boucher,, Aaron Robert; Lic. No.: NA89941 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2025 | Approved | RONNIE MINDANAO |
| Pre-Inspection | 9/18/2025 | Partial Inspection | RAUL BARAJAS |
| Pre-Inspection | 9/19/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 9/26/2025 | Corrections Issued | RONNIE MINDANAO |
| Sewer | 10/1/2025 | Approved | RONNIE MINDANAO |
| Wood Frame | 10/16/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/6/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 11/6/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/10/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 11/10/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 11/13/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Rough | 11/13/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Approved | RONNIE MINDANAO |
| Insulation | 12/1/2025 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 12/17/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/19/2025 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 12/23/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 3/23/2026 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Final | 4/21/2026 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Final | 4/21/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 5/7/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 5/7/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 5/7/2026 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/28/2026 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 5/28/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 5/28/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 6/1/2026 | Approved | JOSH MEISTER |
| HVAC-Final | 6/1/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 6/1/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 6/3/2026 | Approved | RONNIE MINDANAO |
| Final | 6/3/2026 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 6/3/2026 | Approved | RONNIE MINDANAO |
| Green Building Rough | 6/3/2026 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 6/3/2026 | Approved | RONNIE MINDANAO |
| Final | 6/9/2026 | OK to Issue CofO | SCOTT FINNILA |