522 W 98TH ST 90044

Certificate Information: 522 W 98TH ST 90044

Application / Permit
24016-10000-33822
Plan Check / Job No.
B24LA28401
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: GARAGE CONVERSION TO ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/7/2026
Issuing Office
Metro
Current Status
Issued on 5/7/2026

Permit Application Status History

Submitted 11/5/2024 APPLICANT
Assigned to Plan Check Engineer 11/8/2024 SERGIO MUNIZ
Corrections Issued 11/12/2024 SERGIO MUNIZ
Applicant returned to address corrections 6/18/2025 SERGIO MUNIZ
Applicant returned to address corrections 7/1/2025 SERGIO MUNIZ
Plan Check Approved 7/11/2025 GURUNATH NESARAJAH
No Progress 11/3/2025 GURUNATH NESARAJAH
Plan Check Approved 11/3/2025 GURUNATH NESARAJAH
Issued 5/7/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/9/2025 CELINA MORENO
Sewer availability Cleared 1/9/2025 CELINA MORENO
Construction within easement Cleared 2/13/2025 ENRIQUE ACOSTA
Eng Process Fee Ord 176,300 Cleared 6/3/2025 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI