2484 W LOY LANE 90041
Certificate Information: 2484 W LOY LANE 90041
- Application / Permit
- 24016-10000-33654
- Plan Check / Job No.
- B24LA28207
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING ACCESSORY STORAGE STRUCTURE TO AN ADU PER STATE LAW GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | MINA HABILI |
| Corrections Issued | 10/26/2024 | MINA HABILI |
| Building Plans Picked Up | 10/29/2024 | APPLICANT |
| Plan Check Approved | 12/9/2024 | ZAW HAN |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 12/3/2025 | DAVID WILLIAMS |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
| CofO Issued | 12/4/2025 | DEROLD HAUFF |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 11/26/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2024 | AMBER CAMPBELL |
Contact Information
| Architect | Herron,, Elizabeth Anne; Lic. No.: C15167 | 935 W AVE 37 LOS ANGELES, CA 900653241 |
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Sewer | 3/4/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 6/6/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/25/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 6/25/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 6/25/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 6/25/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 7/10/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Insulation | 7/10/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 7/30/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 7/30/2025 | Approved | DAVID WILLIAMS |
| Shower Pan | 7/30/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 8/22/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/21/2025 | Approved | DAVID WILLIAMS |
| Final | 11/21/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 11/21/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 11/21/2025 | Approved | DAVID WILLIAMS |
| Final | 12/3/2025 | OK to Issue CofO | DAVID WILLIAMS |