3966 S CLOVERDALE AVE 90008

Certificate Information: 3966 S CLOVERDALE AVE 90008

Application / Permit
24016-10000-33339
Plan Check / Job No.
B24LA27803
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR + EXTERIOR REMODEL AND ALTERATIONS, REPLACING ALL WINDOWS AND EXTERIOR DOORS, REMOVE WALLS, RELOCATE KITCHEN, ADD LAUNDRY AT 2ND FLOOR, REMODEL ALL BATHROOMS, CONVERT GARAGE ROOF TO DECK/BALCONY.REDUCE 3 CAR GARAGE INTO 2
Permit Issued
Issued on 11/27/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 VARAND SARKISIAN
Corrections Issued 10/28/2024 VARAND SARKISIAN
Quality Review Completed 10/29/2024 KEN GILL
Building Plans Picked Up 10/31/2024 APPLICANT
Plan Check Approved 11/21/2024 VARAND SARKISIAN
Issued 11/27/2024 APPLICANT
CofO in Progress 11/26/2025 LUIS CASTRO
No Progress 11/26/2025 LUIS CASTRO
CofO in Progress 11/26/2025 LUIS CASTRO
No Progress 1/5/2026 DEROLD HAUFF
CofO in Progress 1/5/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF
CofO Issued 1/13/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/1/2024 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 11/1/2024 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 11/19/2024 STEVEN JIN

Contact Information

Contractor Servistar Construction; Lic. No.: 910993-B 13351 RIVERSIDE DRIVE 414      SHERMAN OAKS, CA 91423
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 1/10/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 1/10/2025 Approved LUIS CASTRO
PLUMBING-Rough 4/17/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 4/29/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved LUIS CASTRO
HVAC-Rough 4/29/2025 Approved LUIS CASTRO
METHANE-Rough 4/29/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 5/2/2025 Approved LUIS CASTRO
Shower Pan 5/2/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 5/27/2025 Partial Approval LUIS CASTRO
Insulation 6/2/2025 Conditional Approval LUIS CASTRO
Interior/Exterior Lathing 6/2/2025 Approved LUIS CASTRO
Drywall Nailing 6/10/2025 Approved ALEX COLIN
PLUMBING-Final 11/10/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 11/10/2025 Not Ready for Inspection MICHAEL LEWIS
HVAC-Final 11/17/2025 Approved LUIS CASTRO
ELECTRICAL-Final 11/21/2025 Approved LUIS CASTRO
Final 11/25/2025 OK to Issue CofO LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 11/25/2025 Approved LUIS CASTRO