3942 S DUBLIN AVE 90008
Certificate Information: 3942 S DUBLIN AVE 90008
- Application / Permit
- 24016-10000-33313
- Plan Check / Job No.
- B24LA27750
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/27/2025
- Issuing Office
- Current Status
- Issued on 10/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 10/25/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 11/4/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/20/2024 | ALEC MOUSAKHANIAN |
| Issued | 10/27/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/28/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/28/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 11/2/2024 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/2/2024 | STEVE MELGAR |
| Sewer availability | Cleared | 11/2/2024 | STEVE MELGAR |
| Public Works-Sewers | Cleared | 11/2/2024 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2024 | STEVE MELGAR |
Contact Information
| Contractor | Green Design Home Services Inc; Lic. No.: 1020792-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2025 | Approved | LUIS CASTRO |
| Wood Frame | 12/12/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/2/2026 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/9/2026 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/19/2026 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 2/19/2026 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2026 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 2/19/2026 | Partial Approval | LUIS CASTRO |
| Special/Order Compliance | 2/19/2026 | Corrections Issued | LUIS CASTRO |
| Pre-Inspection | 3/16/2026 | Partial Approval | LUIS CASTRO |
| Pre-Inspection | 5/14/2026 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 5/26/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 6/4/2026 | Approved | LUIS CASTRO |