4023 W CLAYTON AVE 90027
Certificate Information: 4023 W CLAYTON AVE 90027
- Application / Permit
- 24016-10000-33098
- Plan Check / Job No.
- B24LA27472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing 1-story detached garage to new Accessory Dwelling Unit. per GCS 65852.2 (e)(1)(A) R3 occupancy COMPLY WITH DEPARTMENT ORDER effective date 08/30/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2024 | KELVIN CHUONG |
| Corrections Issued | 10/22/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/13/2024 | ZAW HAN |
| Plan Check Approved | 11/14/2024 | ZAW HAN |
| Issued | 12/12/2024 | APPLICANT |
| Permit Finaled | 3/26/2026 | DANIEL SANCHEZ |
| CofO Issued | 3/26/2026 | DANIEL SANCHEZ |
| Permit Finaled | 3/26/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/26/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/26/2024 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 10/28/2024 | JONATHAN HOM |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/12/2025 | Corrections Issued | JOEL ORDAZ |
| Drywall Nailing | 2/12/2025 | Not Ready for Inspection | JOEL ORDAZ |
| Final | 2/12/2025 | Not Ready for Inspection | JOEL ORDAZ |
| Green Building Final | 2/12/2025 | Not Ready for Inspection | JOEL ORDAZ |
| Green Building Rough | 2/12/2025 | Not Ready for Inspection | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | JOEL ORDAZ |
| Smoke Detectors | 2/12/2025 | Not Ready for Inspection | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Footing/Foundation/Slab | 7/15/2025 | Partial Approval | JONATHAN FRANCHINI |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Corrections Issued | JOEL ORDAZ |
| Interior/Exterior Lathing | 8/1/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Interior/Exterior Lathing | 8/5/2025 | Approved | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Corrections Issued | JOEL ORDAZ |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | JOEL ORDAZ |
| Drywall Nailing | 9/8/2025 | Approved | JOEL ORDAZ |
| Final | 9/8/2025 | Approved | JOEL ORDAZ |
| Green Building Final | 9/8/2025 | Approved | JOEL ORDAZ |
| Green Building Rough | 9/8/2025 | Approved | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | Approved | JOEL ORDAZ |
| Smoke Detectors | 9/8/2025 | Approved | JOEL ORDAZ |
| Final | 12/17/2025 | Partial Approval | JOEL ORDAZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Approved | JOEL ORDAZ |
| Footing/Foundation/Slab | 12/17/2025 | Approved | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | JOEL ORDAZ |