4023 W CLAYTON AVE 90027

Certificate Information: 4023 W CLAYTON AVE 90027

Application / Permit
24016-10000-33098
Plan Check / Job No.
B24LA27472
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing 1-story detached garage to new Accessory Dwelling Unit. per GCS 65852.2 (e)(1)(A) R3 occupancy COMPLY WITH DEPARTMENT ORDER effective date 08/30/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 12/12/2024
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2024 APPLICANT
Assigned to Plan Check Engineer 10/21/2024 KELVIN CHUONG
Corrections Issued 10/22/2024 KELVIN CHUONG
Applicant returned to address corrections 11/13/2024 ZAW HAN
Plan Check Approved 11/14/2024 ZAW HAN
Issued 12/12/2024 APPLICANT
Permit Finaled 3/26/2026 DANIEL SANCHEZ
CofO Issued 3/26/2026 DANIEL SANCHEZ
Permit Finaled 3/26/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 10/26/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 10/26/2024 ADRIAN SANCHEZ
Sewer availability Cleared 10/26/2024 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 10/28/2024 JONATHAN HOM
Eng Process Fee Ord 176,300 Cleared 11/9/2024 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/12/2025 Corrections Issued JOEL ORDAZ
Drywall Nailing 2/12/2025 Not Ready for Inspection JOEL ORDAZ
Final 2/12/2025 Not Ready for Inspection JOEL ORDAZ
Green Building Final 2/12/2025 Not Ready for Inspection JOEL ORDAZ
Green Building Rough 2/12/2025 Not Ready for Inspection JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Ready JOEL ORDAZ
Smoke Detectors 2/12/2025 Not Ready for Inspection JOEL ORDAZ
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Not Ready for Inspection JONATHAN FRANCHINI
Footing/Foundation/Slab 7/15/2025 Partial Approval JONATHAN FRANCHINI
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Corrections Issued JOEL ORDAZ
Interior/Exterior Lathing 8/1/2025 Not Ready for Inspection JONATHAN FRANCHINI
Interior/Exterior Lathing 8/5/2025 Approved JOEL ORDAZ
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Corrections Issued JOEL ORDAZ
BUILDING-Rough-Frame 9/8/2025 Approved JOEL ORDAZ
Drywall Nailing 9/8/2025 Approved JOEL ORDAZ
Final 9/8/2025 Approved JOEL ORDAZ
Green Building Final 9/8/2025 Approved JOEL ORDAZ
Green Building Rough 9/8/2025 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 9/8/2025 Approved JOEL ORDAZ
Smoke Detectors 9/8/2025 Approved JOEL ORDAZ
Final 12/17/2025 Partial Approval JOEL ORDAZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Approved JOEL ORDAZ
Footing/Foundation/Slab 12/17/2025 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved JOEL ORDAZ