1119 S WESTCHESTER PL 90019

Certificate Information: 1119 S WESTCHESTER PL 90019

Application / Permit
24016-10000-33068
Plan Check / Job No.
B24LA27431
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(11) Convent
Work Description
EPLAN Interior renovation of Convent: New elevator , Modify six (6) Resident Units , Remove and replace Windows and exterior Sliding Doors .
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
Permit Finaled on 7/7/2026

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Zoning Architect 10/24/2024 JASON BRAVO
Assigned to Plan Check Engineer 10/31/2024 MICHAEL LOPEZ
Corrections Issued 11/13/2024 MICHAEL LOPEZ
Quality Review Completed 11/15/2024 GARO TELMI
Applicant returned to address corrections 3/5/2025 SAM CHANG
Applicant returned to address corrections 4/22/2025 MICHAEL LOPEZ
Plan Check Approved 4/24/2025 MICHAEL LOPEZ
Issued 4/24/2025 APPLICANT
Permit Finaled 6/26/2026 IAN BLINN

Permit Application Clearance Information

Green Code Cleared 2/11/2025 AARON COSTA
DAS Clearance Cleared 4/7/2025 ELIZABETH TOMS
Zoning Plan Check Cleared 4/16/2025 Samuel Gonzalez

Contact Information

Architect Pence,, Melisa Christine; Lic. No.: NA29539       ,
Contractor Con - Am Inc; Lic. No.: 698311-B       ,
Contractor Conam Building Co; Lic. No.: 698311-B       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Lothrop,, Shawn Duane; Lic. No.: NA5627       ,
Geologist Irvine,, Jon Alan; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/17/2025 Partial Approval CHRISTOPHER BLACKWOOD
Deputy Reinf. Concrete 6/17/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 6/17/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/11/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 7/11/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/25/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 7/25/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Wood Frame 7/25/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Drywall Nailing 8/14/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 8/14/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 8/14/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Deputy Reinf. Concrete 10/2/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 10/2/2025 Partial Approval CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 10/6/2025 Partial Approval PAUL BAZERKANIAN
Deputy Reinf. Concrete 10/8/2025 Partial Approval CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 10/8/2025 Partial Approval CHRISTOPHER BLACKWOOD
Deputy Reinf. Concrete 10/20/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 10/20/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 10/20/2025 Partial Approval CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 10/22/2025 Partial Approval CHRISTOPHER BLACKWOOD
Wood Frame 10/22/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 10/23/2025 Partial Inspection CHRISTOPHER BLACKWOOD
Deputy Reinf. Concrete 10/27/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 10/27/2025 Partial Approval CHRISTOPHER BLACKWOOD
Reinforced Concrete Frame 10/27/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 11/7/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 11/7/2025 Partial Approval CHRISTOPHER BLACKWOOD
Wood Frame 11/7/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 11/12/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 11/12/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 11/20/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 12/3/2025 Partial Approval MARTIN TAVITIAN
Wood Frame 12/3/2025 Not Ready for Inspection MARTIN TAVITIAN
Deputy Drilled-In Anchors 12/8/2025 Approved LUIS CCAMACHO
Light Gage Steel Frame 12/8/2025 Partial Approval LUIS CCAMACHO
Wall Anchors 12/8/2025 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 12/10/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 12/17/2025 Conditional Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 12/19/2025 Partial Approval CHRISTOPHER BLACKWOOD
Structural Steel Frame 1/9/2026 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 1/14/2026 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 1/20/2026 Partial Approval IAN BLINN
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Not Ready for Inspection IAN BLINN
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Partial Approval IAN BLINN
Drywall Nailing 1/29/2026 Partial Approval IAN BLINN
Insulation 1/29/2026 Partial Approval IAN BLINN
Drywall Nailing 2/4/2026 Partial Approval IAN BLINN
Drywall Nailing 2/12/2026 Partial Approval IAN BLINN
Light Gage Steel Frame 2/12/2026 Partial Approval IAN BLINN
Drywall Nailing 2/17/2026 Partial Approval IAN BLINN
T-Bar Ceiling 3/11/2026 Partial Approval IAN BLINN
Reinforced Concrete Frame 3/17/2026 Partial Approval IAN BLINN
Light Gage Steel Frame 3/26/2026 Partial Approval IAN BLINN
Drywall Nailing 4/1/2026 Partial Approval IAN BLINN
Pre-Inspection 5/11/2026 Partial Inspection CHRISTOPHER BLACKWOOD
Final 6/26/2026 Permit Finaled IAN BLINN
Green Building Final 6/26/2026 Approved IAN BLINN
SGSOV-Seismic Gas S/O Valve 6/26/2026 SGSOV Approved IAN BLINN
Smoke Detectors 6/26/2026 Approved IAN BLINN