724 N HARVARD BLVD 90029

Certificate Information: 724 N HARVARD BLVD 90029

Application / Permit
24016-10000-32972
Plan Check / Job No.
B24LA27328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) detached 3-car garage & storage to (N) Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/31/2025
Issuing Office
Current Status
Issued on 3/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/16/2024 APPLICANT
Assigned to Plan Check Engineer 10/21/2024 AMY GUEVARRA
Corrections Issued 10/27/2024 AMY GUEVARRA
Applicant returned to address corrections 12/31/2024 REZA HAGHIGHAT
Plan Check Approved 1/18/2025 REZA HAGHIGHAT
Issued 3/31/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/3/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 1/3/2025 TREVOR QUAN
Sewer availability Cleared 1/3/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/13/2025 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hoerner,, John Brent; Lic. No.: NA2145       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/18/2025 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 4/22/2025 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/24/2025 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 6/5/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 6/5/2025 Approved JEFFREY MEAD
Green Building Rough 6/5/2025 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 6/5/2025 Corrections Issued JEFFREY MEAD
MERV13>=Rough 6/5/2025 Approved JEFFREY MEAD
PLUMBING-Rough 6/5/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/18/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 7/18/2025 Corrections Issued BARRY HACHE
HVAC-Rough 7/18/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 7/24/2025 Corrections Issued JEFFREY MEAD
Green Building Rough 7/24/2025 Approved JEFFREY MEAD
Insulation 7/24/2025 Approved JEFFREY MEAD
Drywall Nailing 8/4/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 8/4/2025 Corrections Issued JEFFREY MEAD
Shower Pan 8/15/2025 Approved JEFFREY MEAD
ELECTRICAL-Final 2/5/2026 Corrections Issued JEFFREY MEAD
PLUMBING-Final 2/5/2026 Approved JEFFREY MEAD
Interior/Exterior Lathing 5/1/2026 Approved JEFFREY MEAD
BUILDING-Rough-Frame 5/8/2026 Approved JEFFREY MEAD
ELECTRICAL-Final 5/8/2026 Approved JEFFREY MEAD
Final 5/8/2026 Corrections Issued JEFFREY MEAD
HVAC-Final 5/8/2026 Approved JEFFREY MEAD
ELECTRICAL-Final 5/15/2026 Approved JEFFREY MEAD
Final 5/15/2026 Partial Inspection JEFFREY MEAD
Green Building Final 5/15/2026 Approved JEFFREY MEAD
HVAC-Final 5/15/2026 Approved JEFFREY MEAD
MERV13>=Final 5/15/2026 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved JEFFREY MEAD
Smoke Detectors 5/15/2026 Approved JEFFREY MEAD