1728 W 52ND ST 90062
Certificate Information: 1728 W 52ND ST 90062
- Application / Permit
- 24016-10000-32739
- Plan Check / Job No.
- B24LA25993
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERSION OF (E) EXISTING GARAGE & STORAGE TO A 1-STORY ADU. DETACHED ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c), (d), and (g). STRUCTURAL CHANGES PER WFPP.
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | ADRIANA LOPEZ |
| Corrections Issued | 10/12/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 10/23/2024 | YOUNG KIM |
| Applicant returned to address corrections | 12/24/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 1/7/2025 | ADRIANA LOPEZ |
| No Progress | 1/13/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 1/13/2025 | ADRIANA LOPEZ |
| Issued | 1/13/2025 | APPLICANT |
| CofO in Progress | 5/3/2026 | RAUL BARAJAS |
| No Progress | 5/5/2026 | DEROLD HAUFF |
| CofO in Progress | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| CofO Issued | 5/8/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 10/29/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/29/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2024 | CHRISTINA BRACO |
| Community Plan Implem. Overlay | Cleared | 11/6/2024 | MANERI ROMAN |
Contact Information
| Contractor | R D B & Sons Construction Inc; Lic. No.: 960735-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2025 | Corrections Issued | BARRY HACHE |
| Special/Order Compliance | 1/27/2025 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 8/5/2025 | Partial Approval | BARRY HACHE |
| Footing/Foundation/Slab | 10/20/2025 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/4/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 12/8/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 12/9/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 12/9/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 12/18/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2025 | Partial Inspection | RAUL BARAJAS |
| Insulation | 12/26/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/26/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Approved | OSVALDO PARAMO |
| Insulation | 1/2/2026 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 1/2/2026 | Partial Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 1/5/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/5/2026 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 1/6/2026 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 1/6/2026 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 1/7/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 1/7/2026 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 1/8/2026 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | BARRY HACHE |
| Green Building Rough | 1/9/2026 | Approved | BARRY HACHE |
| Insulation | 1/12/2026 | Approved | BARRY HACHE |
| Drywall Nailing | 1/15/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/12/2026 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 3/3/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 3/5/2026 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 3/10/2026 | No Access for Inspection | ALEX COLIN |
| Underground Mechanical | 3/11/2026 | Approved | BARRY HACHE |
| PLUMBING-Final | 3/17/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 3/18/2026 | Approved | BARRY HACHE |
| Final | 3/18/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 3/23/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 3/26/2026 | Approved | BARRY HACHE |
| Green Building Final | 4/9/2026 | Approved | RAUL BARAJAS |
| Final | 4/17/2026 | No Access for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 4/17/2026 | Approved | RAUL BARAJAS |
| Final | 4/21/2026 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | RAUL BARAJAS |
| Final | 5/1/2026 | OK to Issue CofO | RAUL BARAJAS |