110 S FAIRFAX AVE A-17 90036
Certificate Information: 110 S FAIRFAX AVE A-17 90036
- Application / Permit
- 24016-10000-32699
- Plan Check / Job No.
- B24LA27075
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- eplan: CHANGE IN STORE FRONT TO REVISE ROOF AND STORE FRONT , SEE COMMENTS
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/14/2025
Permit Application Status History
| Submitted | 10/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/24/2024 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/24/2024 | OMID HEDAYAT |
| Assigned to Zoning Architect | 10/31/2024 | NEVRIK NAVASARTIAN |
| Applicant returned to address corrections | 12/2/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/14/2025 | MOHAMMAD ESMAILI |
| Issued | 2/5/2025 | APPLICANT |
| Permit Finaled | 10/8/2025 | MARTIN TAVITIAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/1/2024 | NORLITO MEDRANO |
| "Q" conditions | Cleared | 11/6/2024 | DANIEL CORONADO |
| "T" removal | Cleared | 11/6/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 11/6/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 1/2/2025 | LAKSHMI GANGAMREDDYPALL |
| Miscellaneous | Cleared | 1/2/2025 | LAKSHMI GANGAMREDDYPALL |
| Zoning Plan Check | Cleared | 1/8/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Architect | Coats,, Jason L; Lic. No.: NA39837 | , |
| Contractor | Rich Contracting Company Llc; Lic. No.: 1079865-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 8/4/2025 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 8/4/2025 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/4/2025 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 8/20/2025 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 9/4/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 9/5/2025 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 10/8/2025 | Permit Finaled | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 10/8/2025 | Approved | MARTIN TAVITIAN |