4131 W DUNDEE DR 90027

Certificate Information: 4131 W DUNDEE DR 90027

Application / Permit
24016-10000-32497
Plan Check / Job No.
B24LA26787
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan]NEW ADDITION AND INTERIOR REMODELING TO (E) SFD.
Permit Issued
Issued on 12/9/2024
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 MAHNAZ NOURHASHEMI
Corrections Issued 10/14/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 10/18/2024 TU HUA
Applicant returned to address corrections 11/6/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 12/6/2024 MAHNAZ NOURHASHEMI
Issued 12/9/2024 APPLICANT
CofO in Progress 10/2/2025 ENRIQUE MIRELES
Permit Finaled 10/4/2025 DEROLD HAUFF
Permit Finaled 10/4/2025 DEROLD HAUFF
CofO Issued 10/4/2025 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 10/23/2024 NOAH MCCOY
Grading Pre-Inspection Cleared 11/14/2024 MICHAEL TEMPLE

Contact Information

Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/24/2024 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 12/30/2024 Approved ENRIQUE MIRELES
Deputy Steel/Welding 1/21/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/7/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 2/7/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 2/7/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/7/2025 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 2/10/2025 Approved ENRIQUE MIRELES
HVAC-Rough 2/12/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/12/2025 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 2/19/2025 Approved ENRIQUE MIRELES
Insulation 2/26/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/28/2025 Approved ENRIQUE MIRELES
Shower Pan 2/28/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 3/3/2025 Approved ENRIQUE MIRELES
Drywall Nailing 3/7/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/13/2025 Approved ENRIQUE MIRELES
Final 7/1/2025 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 7/1/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 8/28/2025 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/28/2025 Approved ENRIQUE MIRELES
Smoke Detectors 8/28/2025 Approved ENRIQUE MIRELES