8007-8009 S READING AVE 90045
Certificate Information: 8007-8009 S READING AVE 90045
- Application / Permit
- 24016-10000-32464
- Plan Check / Job No.
- B24LA26742
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE INTO (N) ADU PER GCS 65852.2(e)(1)(A) TO (E) SFD NFPA 13-D FIRE SPRINKLERES REQUIRED THROUGH OUT
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Current Status
- CofO Issued on 5/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/16/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/29/2024 | LUISANGEL VALENZUELA |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 5/4/2026 | JESUS PINEDA |
| Permit Finaled | 5/6/2026 | RICHARD STEINBACH |
| CofO Issued | 5/6/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/6/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 10/17/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | DIANA RENTERIA |
| Specific Plan | Cleared | 10/24/2024 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 10/25/2024 | CHARLES POWELL |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Guideline Builders Inc; Lic. No.: 1021305-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/17/2025 | Partial Approval | JESUS PINEDA |
| Sewer | 11/17/2025 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 11/19/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/1/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 12/1/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/1/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 12/1/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/4/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 12/10/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/10/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/10/2025 | Partial Approval | JESUS PINEDA |
| Wood Frame | 12/10/2025 | Approved | JESUS PINEDA |
| Insulation | 12/11/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 12/17/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/17/2025 | Approved | JESUS PINEDA |
| Final | 4/23/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/23/2026 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 4/23/2026 | Approved | JESUS PINEDA |
| Final | 5/4/2026 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 5/4/2026 | Approved | JESUS PINEDA |