616-616 1/2 W 76TH ST 90044

Certificate Information: 616-616 1/2 W 76TH ST 90044

Application / Permit
24016-10000-32400
Plan Check / Job No.
B24LA26651
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTER BUILDING AT REAR OF LOT. CONVERT ATTACHED GARAGE TO ATTACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 11/8/2024
Issuing Office
Metro
Current Status
Issued on 11/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 CARLOS MONTES
Corrections Issued 10/16/2024 CARLOS MONTES
Building Plans Picked Up 10/16/2024 APPLICANT
Applicant returned to address corrections 10/24/2024 JOSE VELAZQUEZ
Plan Check Approved 10/30/2024 JOSEPH RAFOLS
Issued 11/8/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/23/2024 RICARDO BOHORQUEZ
"Q" conditions Cleared 10/24/2024 JASON CHAN
Sewer availability Cleared 10/28/2024 JUSTIN BICOL
Address approval Cleared 10/29/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/30/2024 BIJAN ZADEH

Contact Information

Contractor Owner-Builder       ,
Engineer Benavides,, Jose Alexander; Lic. No.: C72968 644 N POPLAR ST UNIT B      ORANGE, CA 92868

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/30/2025 Conditional Approval JOHN QUINTANILLA
Footing/Foundation/Slab 1/31/2025 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Rough 1/31/2025 No Access for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 2/3/2025 Approved JOAQUIN GREENOUGH
Underground Mechanical 2/3/2025 Partial Approval JOAQUIN GREENOUGH
Pre-Inspection 2/10/2025 Partial Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 3/19/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 3/19/2025 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 3/19/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 3/19/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 3/21/2025 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 3/21/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 3/21/2025 Approved JOHN QUINTANILLA
Underground Mechanical 3/21/2025 Partial Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 3/26/2025 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 3/26/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Approved JOHN QUINTANILLA
Green Building Rough 3/26/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 3/26/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 4/1/2025 Approved JOHN QUINTANILLA
HVAC-Rough 4/1/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 4/1/2025 Approved JOHN QUINTANILLA
Insulation 4/9/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/18/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 7/11/2025 Approved JOHN QUINTANILLA
Final 7/11/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 7/11/2025 Approved JOHN QUINTANILLA
Green Building Rough 7/11/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 7/11/2025 Approved JOHN QUINTANILLA
Final 7/16/2025 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved JOHN QUINTANILLA