1839 W LOWE ST 1-4 90039
Certificate Information: 1839 W LOWE ST 1-4 90039
- Application / Permit
- 24016-10000-32391
- Plan Check / Job No.
- B24LA26640
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2 (e)(1)(c).
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- CofO Issued on 10/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Zoning Architect | 10/17/2024 | LY CHEA |
| Assigned to Plan Check Engineer | 10/24/2024 | MICHAEL LOPEZ |
| Corrections Issued | 11/5/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 11/14/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 1/22/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/31/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 2/5/2025 | MICHAEL LOPEZ |
| Issued | 2/6/2025 | APPLICANT |
| CofO in Progress | 10/21/2025 | RONALD JIMENEZ |
| Permit Finaled | 10/22/2025 | ERNESTO CORRAL |
| CofO Issued | 10/22/2025 | ERNESTO CORRAL |
| Permit Finaled | 10/22/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 11/24/2024 | JESSICA OPINION |
| Green Code | Cleared | 12/3/2024 | Daniel Smiley |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2024 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 12/24/2024 | KORNEL LELEA |
| Zoning Plan Check | Cleared | 1/23/2025 | Daniel Smiley |
Contact Information
| Contractor | Bek & Bek Inc; Lic. No.: 1056403-B | , |
| Contractor | So-Cal Construction & Electric; Lic. No.: 1056403-B | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2025 | Approved | RAFAEL CORTES |
| Green Building Final | 6/2/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Rough | 6/2/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 6/2/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Rough | 6/6/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 6/6/2025 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 6/11/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 6/11/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 6/11/2025 | Approved | RONALD JIMENEZ |
| Insulation | 6/20/2025 | Approved | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 6/20/2025 | Approved | JEROME BLACKWOOD |
| Drywall Nailing | 6/26/2025 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 6/26/2025 | Conditional Approval | RAFAEL CORTES |
| Final | 9/2/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 9/2/2025 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 9/2/2025 | Approved | RONALD JIMENEZ |
| Final | 10/8/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 10/21/2025 | OK to Issue CofO | RONALD JIMENEZ |