334-334 1/2 N CRANE BLVD 90065

Certificate Information: 334-334 1/2 N CRANE BLVD 90065

Application / Permit
24016-10000-32037
Plan Check / Job No.
B24LA26176
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Convert existing basement into ADU, 403 s.f. per state law. "COMPLY WITH DEPARTMENT ORDER effective date 09/06/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 994813.
Permit Issued
Issued on 11/29/2024
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 NGHI SU
Corrections Issued 10/12/2024 NGHI SU
Plan Check Approved 11/27/2024 NGHI SU
Issued 11/29/2024 APPLICANT
CofO in Progress 6/4/2025 JACOB SEGURA
CofO Issued 6/20/2025 DANIEL SANCHEZ
Permit Finaled 6/20/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/28/2024 WALLIE JONG
Address approval Cleared 10/29/2024 WALLIE JONG
Sewer availability Cleared 10/29/2024 WALLIE JONG
Specific Plan Cleared 10/31/2024 PABLO ESTRADA

Contact Information

Architect Solis,, Otoniel; Lic. No.: C34216 4701 GLENALBYN DR      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/17/2024 Corrections Issued JACOB SEGURA
ELECTRICAL-Final 12/17/2024 Not Ready for Inspection JACOB SEGURA
Final 12/17/2024 Not Ready for Inspection JACOB SEGURA
HVAC-Final 12/17/2024 Not Ready for Inspection JACOB SEGURA
Order to Comply 12/17/2024 Not Required JACOB SEGURA
PLUMBING-Final 12/17/2024 Not Ready for Inspection JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Not Ready JACOB SEGURA
Smoke Detectors 12/17/2024 Not Ready for Inspection JACOB SEGURA
Pre-Inspection 12/19/2024 Approved JACOB SEGURA
BUILDING-Rough-Frame 1/6/2025 Corrections Issued JACOB SEGURA
Final 1/6/2025 Not Ready for Inspection JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Not Ready JACOB SEGURA
Smoke Detectors 1/6/2025 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 1/28/2025 Conditional Approval ROBERT MINASSIANS
Final 1/28/2025 Corrections Issued ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved ROBERT MINASSIANS
Smoke Detectors 1/28/2025 Approved ROBERT MINASSIANS
BUILDING-Rough-Frame 4/3/2025 Not Ready for Inspection JACOB SEGURA
Final 4/3/2025 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 5/15/2025 Approved JACOB SEGURA
Final 5/15/2025 Conditional Approval JACOB SEGURA
Footing/Foundation/Slab 5/15/2025 Approved JACOB SEGURA
Rough-Elec/Plmb/HVAC 5/15/2025 Approved JACOB SEGURA
ELECTRICAL-Final 6/4/2025 Approved JACOB SEGURA
Final 6/4/2025 OK to Issue CofO JACOB SEGURA
HVAC-Final 6/4/2025 Approved JACOB SEGURA
PLUMBING-Final 6/4/2025 Approved JACOB SEGURA