4190-4190 1/4 E YORK BLVD 90065
Certificate Information: 4190-4190 1/4 E YORK BLVD 90065
- Application / Permit
- 24016-10000-32031
- Plan Check / Job No.
- B24LA26170
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: convert existing attached garage into JADU in existing single family dewlling per engineer design (Junior ADU per State Law, CA Govt. Code 65852.2(e)(1)(A) and 65852.22)
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2024 | AUNG SOE |
| Corrections Issued | 10/21/2024 | AUNG SOE |
| Applicant returned to address corrections | 2/5/2025 | NGHI SU |
| Plan Check Approved | 2/13/2025 | NGHI SU |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | DAVID WILLIAMS |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
| CofO Issued | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/24/2024 | GERMAN RODRIGUEZ MENDO |
| Address approval | Cleared | 10/31/2024 | CELINA MORENO |
| Sewer availability | Cleared | 10/31/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2024 | CELINA MORENO |
| Supp. Use District POD/CDO/TDO | Cleared | 12/16/2024 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/3/2025 | Conditional Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Insulation | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| MERV13>=Rough | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Rough | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Pre-Inspection | 5/5/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/19/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/19/2025 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/19/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/19/2025 | Approved | DAVID WILLIAMS |
| MERV13>=Rough | 5/19/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Rough | 5/19/2025 | Corrections Issued | DAVID WILLIAMS |
| Shower Pan | 5/19/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 5/30/2025 | Conditional Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 6/2/2025 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 6/2/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/26/2025 | Not Ready for Inspection | REGINA MENDEZ |
| BUILDING-Rough-Frame | 6/30/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| MERV13>=Rough | 6/30/2025 | Approved | DAVID WILLIAMS |
| Insulation | 7/1/2025 | No Access for Inspection | GEM DE OCAMPO |
| Insulation | 7/3/2025 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 7/14/2025 | Approved | DAVID WILLIAMS |
| Final | 10/27/2025 | Corrections Issued | DAVID WILLIAMS |
| MERV13>=Final | 10/27/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 10/27/2025 | Approved | DAVID WILLIAMS |
| Final | 11/3/2025 | Corrections Issued | DAVID WILLIAMS |
| Final | 11/13/2025 | OK to Issue CofO | DAVID WILLIAMS |