4190-4190 1/4 E YORK BLVD 90065

Certificate Information: 4190-4190 1/4 E YORK BLVD 90065

Application / Permit
24016-10000-32031
Plan Check / Job No.
B24LA26170
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: convert existing attached garage into JADU in existing single family dewlling per engineer design (Junior ADU per State Law, CA Govt. Code 65852.2(e)(1)(A) and 65852.22)
Permit Issued
Issued on 2/18/2025
Issuing Office
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 AUNG SOE
Corrections Issued 10/21/2024 AUNG SOE
Applicant returned to address corrections 2/5/2025 NGHI SU
Plan Check Approved 2/13/2025 NGHI SU
Issued 2/18/2025 APPLICANT
CofO in Progress 11/13/2025 DAVID WILLIAMS
Permit Finaled 11/14/2025 DEROLD HAUFF
CofO Issued 11/14/2025 DEROLD HAUFF
Permit Finaled 11/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/24/2024 GERMAN RODRIGUEZ MENDO
Address approval Cleared 10/31/2024 CELINA MORENO
Sewer availability Cleared 10/31/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/6/2024 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 12/16/2024 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,
Engineer Ding,, Wenzhuo; Lic. No.: C82891 5205 SUNNY POINT PL      RANCHO PALOS VERDES, CA 90275

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/3/2025 Conditional Approval JOSH MEISTER
BUILDING-Rough-Frame 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
Insulation 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
MERV13>=Rough 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Rough 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
Pre-Inspection 5/5/2025 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 5/19/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 5/19/2025 Corrections Issued DAVID WILLIAMS
Footing/Foundation/Slab 5/19/2025 Not Ready for Inspection DAVID WILLIAMS
Interior/Exterior Lathing 5/19/2025 Approved DAVID WILLIAMS
MERV13>=Rough 5/19/2025 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Rough 5/19/2025 Corrections Issued DAVID WILLIAMS
Shower Pan 5/19/2025 Approved DAVID WILLIAMS
Deputy Drilled-In Anchors 5/30/2025 Conditional Approval JOSH MEISTER
ELECTRICAL-Rough 6/2/2025 Corrections Issued DAVID WILLIAMS
PLUMBING-Rough 6/2/2025 Approved DAVID WILLIAMS
Insulation 6/26/2025 Not Ready for Inspection REGINA MENDEZ
BUILDING-Rough-Frame 6/30/2025 Approved DAVID WILLIAMS
Insulation 6/30/2025 Not Ready for Inspection DAVID WILLIAMS
MERV13>=Rough 6/30/2025 Approved DAVID WILLIAMS
Insulation 7/1/2025 No Access for Inspection GEM DE OCAMPO
Insulation 7/3/2025 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved DAVID WILLIAMS
Drywall Nailing 7/14/2025 Approved DAVID WILLIAMS
Final 10/27/2025 Corrections Issued DAVID WILLIAMS
MERV13>=Final 10/27/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 10/27/2025 Approved DAVID WILLIAMS
Final 11/3/2025 Corrections Issued DAVID WILLIAMS
Final 11/13/2025 OK to Issue CofO DAVID WILLIAMS