7810 S ALTAVAN AVE 90045

Certificate Information: 7810 S ALTAVAN AVE 90045

Application / Permit
24016-10000-31907
Plan Check / Job No.
B24LA26028
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN:CONVERT (E) RECREATION ROOM PORTION AT 2ND LEVEL OF (E) 2 STORY REC ROOM WITH ATTACHED GARAGE BELOW INTO (N) 448 SF ADU PER GCS 65852.2 (e)(1)(A).
Permit Issued
Issued on 12/6/2024
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 LUISANGEL VALENZUELA
Corrections Issued 10/11/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/29/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 11/5/2024 LUISANGEL VALENZUELA
Plan Check Approved 12/4/2024 LUISANGEL VALENZUELA
Issued 12/6/2024 APPLICANT
CofO in Progress 7/22/2025 DAVID FEILER
Permit Finaled 7/22/2025 RICHARD STEINBACH
Permit Finaled 7/22/2025 RICHARD STEINBACH
CofO Issued 7/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/17/2024 DIANA RENTERIA
Sewer availability Cleared 10/17/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 10/22/2024 DIANA RENTERIA
Construction near power lines Cleared 11/26/2024 RIDWAN HARDY

Contact Information

Contractor C T West Construction Inc; Lic. No.: 974403-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 1/27/2025 Partial Approval BOBBY KEY
ELECTRICAL-Rough 2/18/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 2/18/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 2/18/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 2/19/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/11/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 4/11/2025 Not Ready for Inspection JESUS PINEDA
Final 4/11/2025 Corrections Issued JESUS PINEDA
HVAC-Final 4/11/2025 Not Ready for Inspection JESUS PINEDA
METHANE-Final 4/11/2025 Not Ready for Inspection JESUS PINEDA
METHANE-Rough 4/11/2025 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 4/11/2025 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 4/11/2025 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 4/22/2025 Approved JESUS PINEDA
ELECTRICAL-Final 4/22/2025 Approved JESUS PINEDA
Final 4/22/2025 Corrections Issued JESUS PINEDA
HVAC-Final 4/22/2025 Approved JESUS PINEDA
PLUMBING-Final 4/22/2025 Corrections Issued JESUS PINEDA
Smoke Detectors 4/22/2025 Approved JESUS PINEDA
Final 6/6/2025 Not Ready for Inspection JESUS PINEDA
PLUMBING-Final 6/6/2025 Approved JESUS PINEDA
Sewer 6/18/2025 Approved JAYLIN GRAVITTE
Final 7/22/2025 OK to Issue CofO DAVID FEILER