1726 W 52ND ST 90062

Certificate Information: 1726 W 52ND ST 90062

Application / Permit
24016-10000-31880
Plan Check / Job No.
B24LA25993
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. INTERIOR REMODEL to (E) SFD including bedroom remodel , kitchen remodel & adding new bedroom .
Permit Issued
Issued on 1/10/2025
Issuing Office
Current Status
Permit Finaled on 4/21/2026

Permit Application Status History

Submitted 10/9/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 ADRIANA LOPEZ
Corrections Issued 10/12/2024 ADRIANA LOPEZ
Quality Review Completed 10/23/2024 YOUNG KIM
Applicant returned to address corrections 12/24/2024 ADRIANA LOPEZ
Plan Check Approved 1/7/2025 ADRIANA LOPEZ
Issued 1/10/2025 APPLICANT
Permit Finaled 4/20/2026 ALEX COLIN

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 11/6/2024 MANERI ROMAN

Contact Information

Contractor R D B & Sons Construction Inc; Lic. No.: 960735-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/7/2025 Corrections Issued BARRY HACHE
HVAC-Rough 5/7/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 5/7/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 8/26/2025 No Access for Inspection BARRY HACHE
ELECTRICAL-Rough 8/26/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 9/5/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 9/15/2025 Corrections Issued BARRY HACHE
HVAC-Rough 9/15/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 9/15/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 9/17/2025 Approved BARRY HACHE
HVAC-Rough 9/17/2025 Approved BARRY HACHE
PLUMBING-Rough 9/17/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 9/18/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 9/19/2025 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 9/22/2025 Partial Approval BARRY HACHE
BUILDING-Rough-Frame 9/24/2025 Approved JOSH MEISTER
Insulation 9/24/2025 Approved JOSH MEISTER
Drywall Nailing 9/26/2025 Approved RONNIE MEDINA
Shower Pan 10/17/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/21/2025 Partial Approval BARRY HACHE
Shower Pan 11/7/2025 Approved BARRY HACHE
ELECTRICAL-Final 12/17/2025 Corrections Issued BARRY HACHE
HVAC-Rough 1/8/2026 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 2/11/2026 Approved BARRY HACHE
ELECTRICAL-Final 2/24/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 2/25/2026 Approved BARRY HACHE
ELECTRICAL-Final 3/2/2026 Approved RAUL BARAJAS
PLUMBING-Final 3/10/2026 No Access for Inspection BARRY HACHE
PLUMBING-Final 3/11/2026 Corrections Issued BARRY HACHE
PLUMBING-Final 3/17/2026 Approved BARRY HACHE
HVAC-Final 3/23/2026 Approved BARRY HACHE
Final 4/17/2026 No Access for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/17/2026 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 4/17/2026 Approved RAUL BARAJAS
Final 4/20/2026 Permit Finaled ALEX COLIN
SGSOV-Seismic Gas S/O Valve 4/20/2026 SGSOV Approved ALEX COLIN