3744 N VINELAND AVE 91604
Certificate Information: 3744 N VINELAND AVE 91604
- Application / Permit
- 24016-10000-31474
- Plan Check / Job No.
- B24LA25429
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR AND INTERIOR REMODEL TO (E) SINGLE FAMILY DEWLLING WITH ATTACHED GARAGE. NEW DECK ABOVE EXISTING PATIO
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/23/2025
Permit Application Status History
| Submitted | 10/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | AUNG SOE |
| Corrections Issued | 10/8/2024 | AUNG SOE |
| Building Plans Picked Up | 10/9/2024 | APPLICANT |
| Applicant returned to address corrections | 10/15/2024 | SUNMIN LEE |
| Plan Check Approved | 10/24/2024 | JOSEPH RAFOLS |
| Issued | 10/31/2024 | APPLICANT |
| Permit Finaled | 6/23/2025 | CHRISTOPHE COCHRAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/10/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/10/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/15/2024 | AUNG SOE |
| ZI | Cleared | 10/20/2024 | NATHAN ROMINE |
Contact Information
| Contractor | Noah'S Ark Development Inc; Lic. No.: 1050849-B | 10 EDGEBROOK DR POMONA, CA 91766 |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/4/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 11/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/12/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/2/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/2/2024 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 12/2/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 12/6/2024 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 12/6/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/10/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 12/10/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 12/16/2024 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/17/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 12/17/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 1/22/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 1/22/2025 | Corrections Issued | JACK KARGODORIAN |
| Sewer | 1/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 1/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/29/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/29/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 1/29/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/29/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 1/29/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deck | 2/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 2/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 2/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/11/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 2/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 3/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/3/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/16/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| MERV13>=Final | 5/16/2025 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 5/16/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/16/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/27/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 6/12/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 6/23/2025 | Permit Finaled | CHRISTOPHE COCHRAN |