835 W 6TH ST C 90731
Certificate Information: 835 W 6TH ST C 90731
- Application / Permit
- 24016-10000-31285
- Plan Check / Job No.
- B24LA25196
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan CONVERT EXISTING ATTACHED 2-CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE. GARAGE IS ATTACHED TO APARTMENT BUILDING. 1 OF 2
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- Issued on 5/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 10/10/2024 | JASON BRAVO |
| Corrections Issued | 10/22/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 10/24/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 1/2/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/2/2025 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/12/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 5/28/2025 | MICHAEL LOPEZ |
| Issued | 5/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2024 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 10/18/2024 | XOCHITL ARQUIETA |
| Grading Pre-Inspection | Cleared | 11/21/2024 | VASIL MIHALEV |
| Green Code | Cleared | 11/25/2024 | MICHAEL LOPEZ |
| Hydrant and Access approval | Cleared | 1/13/2025 | KENNETH FRASER |
| Miscellaneous | Cleared | 3/17/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 3/17/2025 | ROSALINDA MEZA |
| Zoning Plan Check | Cleared | 4/10/2025 | MICHAEL LOPEZ |
Contact Information
| Contractor | Fredeluces M Company; Lic. No.: 799162-B | , |
| Engineer | Bareng,, Jenn Tamayo; Lic. No.: C79168 | 21301 ERWIN ST #427 WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Insulation | 6/26/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 6/30/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Green Building Rough | 6/30/2025 | Approved | MICHAEL PETRUSKO |
| Insulation | 6/30/2025 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 6/30/2025 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 8/14/2025 | Approved | MICHAEL PETRUSKO |
| Final | 1/20/2026 | Not Ready for Inspection | DAVID TSAU |
| Green Building Final | 1/20/2026 | Not Ready for Inspection | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Ready | DAVID TSAU |
| Smoke Detectors | 1/20/2026 | Not Ready for Inspection | DAVID TSAU |
| Drywall Nailing | 1/29/2026 | Approved | MICHAEL PETRUSKO |
| Final | 5/27/2026 | Corrections Issued | MICHAEL PETRUSKO |
| Green Building Final | 5/27/2026 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 5/27/2026 | Not Ready for Inspection | MICHAEL PETRUSKO |