9219 W ROBIN DR 90069

Certificate Information: 9219 W ROBIN DR 90069

Application / Permit
24016-10000-31030
Plan Check / Job No.
B24LA24479
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
RENOVATION OF (E) DETACHED ACCESSORY REC ROOM STRUCTURE/ALQ TO BECOME A PATIO COVER WITH ATTACHED STORAGE.
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 11/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 JAD BASMA
Corrections Issued 9/28/2024 JAD BASMA
Quality Review Completed 9/30/2024 GARO TELMI
Plan Check Approved 3/6/2025 JAD BASMA
Issued 3/6/2025 APPLICANT
CofO in Progress 11/14/2025 ROY SPAULDING
No Progress 11/14/2025 SCOTT FINNILA
CofO in Progress 11/14/2025 SCOTT FINNILA
CofO in Progress 11/21/2025 ROY SPAULDING
Permit Finaled 11/23/2025 DEROLD HAUFF
Permit Finaled 11/23/2025 DEROLD HAUFF
CofO Issued 11/23/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 11/7/2024 JUSTIN BICOL
Sewer availability Cleared 11/7/2024 JUSTIN BICOL
ZA Case Cleared 11/14/2024 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 11/15/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 2/11/2025 PATRICK PEREZ
GPI Written Notices Cleared 3/5/2025 JAD BASMA
Grading Pre-Inspection Cleared 3/5/2025 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2025 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 4/18/2025 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 4/18/2025 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved RAUL BARAJAS
ELECTRICAL-Rough 5/30/2025 Approved DAVID WILLIAMS
HVAC-Rough 6/2/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 6/9/2025 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 6/10/2025 Approved BRENDAN MORELLI
Insulation 6/10/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 6/10/2025 Approved BRENDAN MORELLI
Drywall Nailing 6/12/2025 Approved BRENDAN MORELLI
Shower Pan 6/25/2025 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Final 10/9/2025 Approved ROY SPAULDING
Final 10/9/2025 Corrections Issued ROY SPAULDING
PLUMBING-Final 10/9/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved ROY SPAULDING
Smoke Detectors 10/9/2025 Approved ROY SPAULDING
Final 11/13/2025 OK to Issue CofO ROY SPAULDING
Final 11/19/2025 OK to Issue CofO ROY SPAULDING