1618 S BEVERLY DR 90035
Certificate Information: 1618 S BEVERLY DR 90035
- Application / Permit
- 24016-10000-30928
- Plan Check / Job No.
- B24LA24745
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan - Interior Remodeling for (E) SFD with foundation work per Engineer calcs
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/24/2026
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2024 | NGHI SU |
| Corrections Issued | 10/2/2024 | NGHI SU |
| Plan Check Approved | 12/3/2024 | KELVIN CHUONG |
| Issued | 4/2/2025 | APPLICANT |
| Permit Finaled | 3/23/2026 | WILBER ROSALES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/8/2024 | VASIL MIHALEV |
Contact Information
| Contractor | Caribe Construction Inc; Lic. No.: 878090-B | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/30/2025 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/1/2025 | Conditional Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/16/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/16/2025 | Conditional Approval | ASHLEY THOMPSON |
| HVAC-Rough | 10/17/2025 | Partial Approval | EVAN COOPER |
| Shower Pan | 10/17/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 11/4/2025 | Approved | EVAN COOPER |
| Insulation | 11/4/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 11/4/2025 | Approved | EVAN COOPER |
| Wood Frame | 11/4/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 11/17/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/17/2025 | Approved | ASHLEY THOMPSON |
| Final | 3/23/2026 | Permit Finaled | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 3/23/2026 | Approved | WILBER ROSALES |