153 E 47TH ST 90011
Certificate Information: 153 E 47TH ST 90011
- Application / Permit
- 24016-10000-30884
- Plan Check / Job No.
- B24LA24700
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED GARAGE AND STORAGE TO ADU PER STATE LAW. ALL WORK PER WFPP
- Permit Issued
- Issued on 1/21/2025
- Issuing Office
- Current Status
- CofO Issued on 2/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | ALEXANDER JOO |
| Corrections Issued | 10/4/2024 | ALEXANDER JOO |
| Building Plans Picked Up | 10/7/2024 | APPLICANT |
| Plan Check Approved | 1/21/2025 | ZAW HAN |
| Issued | 1/21/2025 | APPLICANT |
| CofO in Progress | 2/12/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
| CofO Issued | 2/13/2026 | DEROLD HAUFF |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2024 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/25/2024 | ABEL CASILLAS |
| Construction near power lines | Cleared | 12/9/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2025 | AMBER CAMPBELL |
Contact Information
| Contractor | Soumekh Michael N; Lic. No.: 773770-B | 1140 SOUTH ALFRED STREET LOS ANGELES, CA 90035 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2025 | Partial Inspection | SABAS ALONSO |
| Underground Mechanical | 4/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/22/2025 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/30/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/27/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 6/27/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 6/27/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | WAYNE REGESTER |
| Rough-Elec/Plmb/HVAC | 7/1/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 7/11/2025 | Partial Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 8/1/2025 | Partial Approval | ANTHONY RAMOS |
| Shower Pan | 8/1/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/18/2025 | No Access for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 8/20/2025 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 10/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 11/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 11/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/19/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 11/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/21/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/12/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/12/2026 | Approved | ALEJANDRO DE ARTOLA |