641-641 1/2 N FULLER AVE 90036

Certificate Information: 641-641 1/2 N FULLER AVE 90036

Application / Permit
24016-10000-30788
Plan Check / Job No.
B24LA24546
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert Existing Garage to AN ATTACHED ADU
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/7/2024 CARLOS MONTES
Corrections Issued 10/8/2024 CARLOS MONTES
Plan Check Approved 11/26/2024 DANIEL SANJUAN
Issued 1/23/2025 APPLICANT
CofO in Progress 12/2/2025 JOSH MEISTER
Permit Finaled 12/4/2025 DEROLD HAUFF
CofO Issued 12/4/2025 DEROLD HAUFF
Permit Finaled 12/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/31/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 11/21/2024 AMBER CAMPBELL
Sewer availability Cleared 11/21/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Itani,, Ayman; Lic. No.: C91801 5872 NEWMAN ST      CYPRESS, CA 90630

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 2/5/2025 Not Ready for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Approved JOSE MACIAS
Footing/Foundation/Slab 2/5/2025 Corrections Issued JOSE MACIAS
Wood Frame 2/5/2025 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 7/15/2025 Corrections Issued RONNIE MINDANAO
Wood Frame 7/15/2025 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 9/16/2025 Approved JOSE MACIAS
Wood Frame 9/16/2025 Corrections Issued JOSE MACIAS
Wood Frame 9/25/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 10/3/2025 Approved JOSH MEISTER
PLUMBING-Rough 10/3/2025 Corrections Issued JOSH MEISTER
PLUMBING-Rough 10/8/2025 Approved JOSH MEISTER
Wood Frame 10/8/2025 Not Ready for Inspection JOSH MEISTER
HVAC-Rough 10/14/2025 Conditional Approval JOSH MEISTER
Wood Frame 10/14/2025 Corrections Issued JOSH MEISTER
BUILDING-Rough-Frame 10/16/2025 Approved JOSH MEISTER
METHANE-Rough 10/16/2025 Approved JOSH MEISTER
Insulation 10/20/2025 Corrections Issued JOSH MEISTER
Insulation 10/22/2025 Approved ALEX COLIN
Final 11/3/2025 Corrections Issued JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Not Ready JOSH MEISTER
Smoke Detectors 11/3/2025 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 11/4/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 11/5/2025 Approved JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved JOSH MEISTER
Shower Pan 11/5/2025 Approved JOSH MEISTER
Smoke Detectors 11/5/2025 Corrections Issued JOSH MEISTER
ELECTRICAL-Final 11/6/2025 Not Ready for Inspection JOSH MEISTER
HVAC-Final 11/6/2025 Corrections Issued JOSH MEISTER
PLUMBING-Final 11/6/2025 Approved JOSH MEISTER
ELECTRICAL-Final 11/10/2025 Corrections Issued RONNIE MINDANAO
Final 11/10/2025 Corrections Issued RONNIE MINDANAO
HVAC-Final 11/10/2025 Corrections Issued RONNIE MINDANAO
Smoke Detectors 11/10/2025 Approved RONNIE MINDANAO
ELECTRICAL-Final 11/13/2025 Approved JOSH MEISTER
HVAC-Final 11/13/2025 Corrections Issued JOSH MEISTER
PLUMBING-Final 11/13/2025 Approved JOSH MEISTER
Final 11/24/2025 Not Ready for Inspection RONNIE MINDANAO
HVAC-Final 11/24/2025 Corrections Issued RONNIE MINDANAO
HVAC-Final 11/26/2025 Approved JOSH MEISTER
Final 12/2/2025 OK to Issue CofO JOSH MEISTER