1106 S HARBOR BLVD B-1A 90731
Certificate Information: 1106 S HARBOR BLVD B-1A 90731
- Application / Permit
- 24016-10000-30581
- Plan Check / Job No.
- B24LA24304
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- Eplan: New Tenant Improvement for a Retail Bakery (The Baked Bear) in the West Harbor Center on the San Pedro Waterfront.
- Permit Issued
- Issued on 2/10/2026
- Issuing Office
- Current Status
- Issued on 2/10/2026
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | CHUNG-WEN CHUANG |
| Assigned to Zoning Architect | 10/3/2024 | NEVRIK NAVASARTIAN |
| Corrections Issued | 10/15/2024 | CHUNG-WEN CHUANG |
| Quality Review Completed | 10/22/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/19/2024 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 12/9/2024 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 1/29/2025 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 2/6/2025 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/7/2025 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 3/19/2025 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/1/2025 | CHUNG-WEN CHUANG |
| Plan Check Approved | 4/11/2025 | CHUNG-WEN CHUANG |
| Issued | 2/10/2026 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/19/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2024 | XOCHITL ARQUIETA |
| "Q" conditions | Cleared | 2/5/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 2/5/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 2/5/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 2/5/2025 | YINGSHI HUANG |
| ZA Case | Cleared | 2/5/2025 | YINGSHI HUANG |
| Address approval | Cleared | 3/17/2025 | ERIK BEASLEY |
| Food Service Establishment | Cleared | 3/17/2025 | KENNETH BROWNE |
| ZA Case | Cleared | 3/19/2025 | EDWIN CANO |
| ZA Case | Cleared | 3/19/2025 | EDWIN CANO |
| Food establishment approval | Cleared | 4/1/2025 | LACDHS APPROVED |
| DAS Clearance | Cleared | 4/3/2025 | Kelvin Chuong |
| Port of LA Approval | Cleared | 4/8/2025 | MELISSA HARNE |
| Zoning Plan Check | Cleared | 4/8/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Architect | Drury,, Robert Matthew; Lic. No.: NA40796 | , |
| Contractor | Dfl Design + Build; Lic. No.: 1046215-B | , |
| Contractor | Dfl Group Llc; Lic. No.: 1046215-B | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/27/2026 | No Access for Inspection | MICHAEL PETRUSKO |
| Deputy Drilled-In Anchors | 4/28/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Excavation/Setback/Form/Re-Bar | 5/5/2026 | Not Ready for Inspection | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 5/6/2026 | Conditional Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 5/7/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 5/7/2026 | Approved | DAVID TSAU |