400 S HOPE ST 1060 90071
Certificate Information: 400 S HOPE ST 1060 90071
- Application / Permit
- 24016-10000-30544
- Plan Check / Job No.
- B24LA24265
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT IN EXISTING OFFICE BUILDING, 10TH FLOOR ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/20/2025
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/28/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/23/2024 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/25/2024 | PINANK PATEL |
| Issued | 11/5/2024 | APPLICANT |
| Permit Finaled | 2/20/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| "D" conditions | Cleared | 10/7/2024 | DANIEL CORONADO |
| CPC | Cleared | 10/7/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 10/7/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 10/7/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 10/7/2024 | DANIEL CORONADO |
| Specific Plan | Cleared | 10/9/2024 | ERICK MORALES |
| Fire Marshal Fire Life Safety | Cleared | 10/23/2024 | MENOA AGHAJANI |
Contact Information
| Architect | Lebrilla,, Ariane; Lic. No.: NA38312 | , |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/18/2024 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 12/30/2024 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 12/30/2024 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 1/29/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| T-Bar Ceiling | 2/4/2025 | Approved | LARRY ARNICK |
| Final | 2/20/2025 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 2/20/2025 | Approved | PAUL BAZERKANIAN |
| Green Building Rough | 2/20/2025 | Approved | PAUL BAZERKANIAN |
| Reinforced Concrete Frame | 2/20/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 2/20/2025 | Approved | PAUL BAZERKANIAN |
| Verify Sprinkler Sign Off | 2/20/2025 | Approved | PAUL BAZERKANIAN |