127 N ST ANDREWS PL 90004
Certificate Information: 127 N ST ANDREWS PL 90004
- Application / Permit
- 24016-10000-30480
- Plan Check / Job No.
- B24LA24182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) 2-STORY SINGLE FAMILY DWELLING AND ENCLOSE (E) 115 SQ FT COVERED PATIO INTO PLAYROOM ON 1ST FLOOR AT REAR
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2024 | LUKE GONZALES |
| Corrections Issued | 9/28/2024 | LUKE GONZALES |
| Building Plans Picked Up | 10/4/2024 | APPLICANT |
| Applicant returned to address corrections | 10/9/2024 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/21/2024 | GEORGE ALVAREZ |
| Plan Check Approved | 12/17/2024 | MINA HABILI |
| Issued | 12/17/2024 | APPLICANT |
| CofO in Progress | 4/15/2025 | JEFFREY MEAD |
| No Progress | 4/19/2025 | DEROLD HAUFF |
| CofO in Progress | 4/19/2025 | DEROLD HAUFF |
| CofO in Progress | 6/16/2025 | RAUL BARAJAS |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
| CofO Issued | 6/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Historic monument | Cleared | 10/28/2024 | RAFAEL FONTES |
Contact Information
| Contractor | Living Los Angeles Construction Inc; Lic. No.: 1066125-B | PO BOX 1916 POMONA, CA 91769 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 2/4/2025 | Conditional Approval | JEFFREY MEAD |
| Pre-Inspection | 2/4/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 2/6/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/6/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 2/6/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 2/6/2025 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 2/11/2025 | Conditional Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/19/2025 | Conditional Approval | JEFFREY MEAD |
| Insulation | 2/21/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/26/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 3/4/2025 | Partial Approval | RONNIE MINDANAO |
| Final | 4/14/2025 | OK to Issue CofO | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/14/2025 | Approved | JEFFREY MEAD |