3411 S 12TH AVE #100 90018

Certificate Information: 3411 S 12TH AVE #100 90018

Application / Permit
24016-10000-30355
Plan Check / Job No.
B24LA24021
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
PROPOSED CHANGE OF USE FROM JOINT LIVING QUARTERS TO TAKE-OUT CAFE SHOP
Permit Issued
Issued on 6/16/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 SINA KHOSRAVI
Assigned to Zoning Architect 9/26/2024 NEVRIK NAVASARTIAN
Corrections Issued 10/1/2024 SINA KHOSRAVI
Quality Review Completed 10/4/2024 KEN GILL
Building Plans Picked Up 10/28/2024 APPLICANT
Plan Check Approved 6/9/2025 SINA KHOSRAVI
Issued 6/16/2025 APPLICANT
CofO in Progress 9/18/2025 ALFREDO LOPEZ
Permit Finaled 9/19/2025 ERNESTO CORRAL
CofO Issued 9/19/2025 ERNESTO CORRAL
Permit Finaled 9/19/2025 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2025 WALLIE JONG
Sewer availability Cleared 4/15/2025 WALLIE JONG
DAS Clearance Cleared 4/17/2025 SINA KHOSRAVI
Food Service Establishment Cleared 4/21/2025 KENNETH BROWNE
ZA Case Cleared 4/25/2025 ASHLEY RODARTE
Community Plan Implem. Overlay Cleared 5/16/2025 ISAIAH ROSS
Historic Resource Verification Cleared 5/19/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 5/19/2025 YASMINE BASHIRI
Zoning Plan Check Cleared 5/27/2025 NEVRIK NAVASARTIAN
Food establishment approval Cleared 6/9/2025 LACDHS APPROVED

Contact Information

Contractor Vhd Construction Inc; Lic. No.: 1065108-B 210 W 1ST ST SUITE 212      SANTA ANA, CA 92701
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 6/24/2025 Partial Inspection ALFREDO LOPEZ
Light Gage Steel Frame 6/24/2025 Partial Approval ALFREDO LOPEZ
Footing/Foundation/Slab 6/25/2025 Approved ALFREDO LOPEZ
Drywall Nailing 6/30/2025 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 8/7/2025 Approved DARRYL ARNOLD
Drywall Nailing 8/11/2025 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Not Ready ALFREDO LOPEZ
Final 9/16/2025 OK to Issue CofO ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 9/16/2025 Approved ALFREDO LOPEZ