919 N FRESNO ST 90063
Certificate Information: 919 N FRESNO ST 90063
- Application / Permit
- 24016-10000-30032
- Plan Check / Job No.
- B24LA23562
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO EXISTING SFD, ADDITION WILL INCLUDE CONVERSION OF CRAWLSPACE INTO AN ATTACHED ACCESSORY DWELLING UNIT PER ORDINANCE TO CREATE 2-STORY BUILDING.
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 10/9/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 10/16/2024 | KEN GILL |
| Building Plans Picked Up | 10/18/2024 | APPLICANT |
| Applicant returned to address corrections | 2/3/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 3/21/2025 | GEORGE JOLAKIAN |
| Issued | 3/21/2025 | APPLICANT |
| CofO in Progress | 9/9/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 9/10/2025 | DEROLD HAUFF |
| CofO Issued | 9/10/2025 | DEROLD HAUFF |
| Permit Finaled | 9/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/21/2024 | NATHAN ROMINE |
| ZI | Cleared | 11/21/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/6/2024 | ADRIAN SANCHEZ |
| Tenant Habitability Plan | Cleared | 12/20/2024 | KORNEL LELEA |
| Address approval | Cleared | 3/21/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guh,, Jeff; Lic. No.: S3218 | 705 SAN VICENTE BLVD SANTA MONICA, CA 90402 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 4/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 5/7/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/7/2025 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/28/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/2/2025 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 6/2/2025 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/4/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/4/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/4/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/1/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/3/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 7/3/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 7/8/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 7/11/2025 | Corrections Issued | ANTHONY RAMOS |
| Green Building Rough | 7/11/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 7/14/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/15/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/15/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/20/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 9/8/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 9/8/2025 | Approved | ALIZAH MAYAGOITIA |