6516-6518 S MENLO AVE 90044

Certificate Information: 6516-6518 S MENLO AVE 90044

Application / Permit
24016-10000-30031
Plan Check / Job No.
B24LA23557
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. (E) ATTACHED GARAGE CONVERSION TO A 384 SF ADU PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 3/17/2025
Issuing Office
Current Status
CofO Issued on 9/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 YASHAR EMAMI
Corrections Issued 9/26/2024 YASHAR EMAMI
Applicant returned to address corrections 10/16/2024 YASHAR EMAMI
Applicant returned to address corrections 10/23/2024 ALFREDO JARA
Applicant returned to address corrections 10/26/2024 ALFREDO JARA
Applicant returned to address corrections 11/6/2024 ALFREDO JARA
Applicant returned to address corrections 12/17/2024 YASHAR EMAMI
Plan Check Approved 1/6/2025 ALFREDO JARA
Issued 3/17/2025 APPLICANT
CofO in Progress 9/22/2025 BARRY HACHE
Permit Finaled 9/27/2025 DEROLD HAUFF
CofO Issued 9/27/2025 DEROLD HAUFF
Permit Finaled 9/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/4/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 10/9/2024 JUSTIN BICOL
Sewer availability Cleared 10/9/2024 JUSTIN BICOL
Address approval Cleared 10/10/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/11/2024 JUSTIN BICOL

Contact Information

Architect Gutierrez,, Juan Antonio; Lic. No.: C33231 15622 PATRONELLA AVENUE      GARDENA, CA 90249
Architect Gutierrez,, Juan Antonio; Lic. No.: NA33231       ,
Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 4/25/2025 Approved WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 5/6/2025 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 5/6/2025 Conditional Approval BARRY HACHE
Excavation/Setback/Form/Re-Bar 5/12/2025 Partial Approval BARRY HACHE
Footing/Foundation/Slab 5/12/2025 Partial Approval BARRY HACHE
Excavation/Setback/Form/Re-Bar 5/29/2025 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/29/2025 Approved MICHAEL LEWIS
HVAC-Rough 6/12/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 6/12/2025 Corrections Issued BARRY HACHE
Underground Mechanical 6/12/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 6/23/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 6/23/2025 Corrections Issued BARRY HACHE
Gas Test 6/23/2025 Approved BARRY HACHE
HVAC-Rough 6/23/2025 Approved BARRY HACHE
Underground Mechanical 6/23/2025 Approved BARRY HACHE
ELECTRICAL-Rough 6/25/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 6/25/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 6/27/2025 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 7/3/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Approved BARRY HACHE
Interior/Exterior Lathing 7/3/2025 Approved BARRY HACHE
Insulation 7/16/2025 Approved BARRY HACHE
Drywall Nailing 8/4/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 8/7/2025 Approved BARRY HACHE
Shower Pan 8/7/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/8/2025 Corrections Issued BARRY HACHE
Green Building Final 9/8/2025 Approved BARRY HACHE
HVAC-Final 9/8/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 9/8/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 9/8/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/16/2025 Approved BARRY HACHE
Final 9/16/2025 Corrections Issued BARRY HACHE
HVAC-Final 9/16/2025 Approved BARRY HACHE
PLUMBING-Final 9/16/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Not Ready BARRY HACHE
Final 9/22/2025 OK to Issue CofO BARRY HACHE
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Approved BARRY HACHE