433 S COLYTON ST 90013

Certificate Information: 433 S COLYTON ST 90013

Application / Permit
24016-10000-29935
Plan Check / Job No.
B24LA23420
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
Eplan Tenant improvment with two new exterior courtyards to existing warehouse. No change of use.
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
Issued on 4/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Zoning Architect 9/26/2024 NEVRIK NAVASARTIAN
Assigned to Plan Check Engineer 10/3/2024 FARSHAD ALIMOHAMADI
Corrections Issued 10/5/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 10/22/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 11/27/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/2/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/19/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/20/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/5/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/15/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 4/16/2025 FARSHAD ALIMOHAMADI
Issued 4/24/2025 APPLICANT

Permit Application Clearance Information

Green Code Cleared 1/14/2025 Luke Gonzales
Zoning Plan Check Cleared 1/27/2025 NEVRIK NAVASARTIAN
DAS Clearance Cleared 2/28/2025 Luke Gonzales

Contact Information

Architect Richmond,, Deborah; Lic. No.: C28542 946 LARKER AVENUE      LOS ANGELES, CA 90042
Contractor Casco Contractors Llc; Lic. No.: 790706-B       ,
Engineer Yu,, Philip Junior Davi; Lic. No.: NA5854       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2025 Approved RONALD JIMENEZ
Pre-Inspection 7/15/2025 Partial Inspection LARRY ARNICK
Pre-Inspection 7/18/2025 Approved RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 7/21/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 8/13/2025 Partial Inspection RONALD JIMENEZ
Footing/Foundation/Slab 8/15/2025 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 8/18/2025 Partial Inspection RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 8/19/2025 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 8/26/2025 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 8/27/2025 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 9/17/2025 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 9/23/2025 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 9/29/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 9/30/2025 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 9/30/2025 Partial Approval RONALD JIMENEZ
Wood Frame 10/8/2025 Partial Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Not Ready for Inspection RONALD JIMENEZ
Piling/Pier/Caisson 10/21/2025 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 10/22/2025 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 10/28/2025 Partial Approval RONALD JIMENEZ
Piling/Pier/Caisson 10/28/2025 Partial Approval RONALD JIMENEZ
Piling/Pier/Caisson 11/3/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/3/2025 Partial Inspection REGINA MENDEZ
Light Gage Steel Frame 1/7/2026 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 1/26/2026 Partial Approval RONALD JIMENEZ
Special/Order Compliance 1/26/2026 Approved SEAN GRIFFITH
Footing/Foundation/Slab 2/9/2026 Not Ready for Inspection REGINA MENDEZ
Excavation/Setback/Form/Re-Bar 2/24/2026 Not Ready for Inspection SEAN POMISH
Excavation/Setback/Form/Re-Bar 2/26/2026 Partial Approval SEAN POMISH
Wood Frame 5/5/2026 Corrections Issued SEAN POMISH
Special/Order Compliance 6/3/2026 Corrections Issued RONALD JIMENEZ