850 S BROADWAY 90014
Certificate Information: 850 S BROADWAY 90014
- Application / Permit
- 24016-10000-29917
- Plan Check / Job No.
- B24LA23387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Theater
- Work Description
- ePlan. Fire rated passthrough of 850 & 846 S. Broadway the proposed scope of work entails cutting an opening through the Orpheum Theatre stage wall allowing a passthrough opening to the adjacent 850 S. Broadway storage space separated by a 2-hour fire rated overhead coiling door. The proposed passthrough will be for service and maintenance to load and unload stage sets and for general stage work. It is not intended to be used by the general public and will be closed during events.
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2025
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 9/19/2024 | BENNY WONG |
| Corrections Issued | 9/25/2024 | HERNAN ARREOLA |
| Quality Review Completed | 9/30/2024 | PETER KIM |
| Applicant returned to address corrections | 10/9/2024 | HERNAN ARREOLA |
| Plan Check Approved | 4/2/2025 | HERNAN ARREOLA |
| Issued | 4/29/2025 | APPLICANT |
| Permit Finaled | 11/4/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| CPC | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| CPC | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| CPC | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| CPC | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| ZI | Cleared | 9/30/2024 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 10/1/2024 | Fernando Flores |
| City Hist. Cultural Monument | Cleared | 10/2/2024 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 10/2/2024 | LAMBERT GIESSINGER |
| ZI | Cleared | 10/8/2024 | LAMBERT GIESSINGER |
| Redevelopment Project Area | Cleared | 10/15/2024 | YASMINE BASHIRI |
| Fire Marshal Fire Life Safety | Cleared | 2/6/2025 | FIRE DEPARTMENT |
| Zoning Plan Check | Cleared | 2/11/2025 | BENNY WONG |
Contact Information
| Architect | Tang,, Paul Reling; Lic. No.: NA24959 | , |
| Contractor | Cuevas & Cuevas Construction Group Inc; Lic. No.: 974311-B | , |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Partial Approval | PAUL BAZERKANIAN |
| Masonry Wall/Backfill | 8/13/2025 | Partial Approval | JEROME BLACKWOOD |
| Final | 11/4/2025 | Permit Finaled | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 11/4/2025 | Approved | PAUL BAZERKANIAN |