1860 W 48TH ST 90062
Certificate Information: 1860 W 48TH ST 90062
- Application / Permit
- 24016-10000-29896
- Plan Check / Job No.
- B24LA23365
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU.
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2024 | MINA HABILI |
| Corrections Issued | 9/18/2024 | MINA HABILI |
| Applicant returned to address corrections | 10/31/2024 | JOSE VELAZQUEZ |
| Plan Check Approved | 11/5/2024 | CRISTINA SALAZAR |
| Issued | 2/26/2025 | APPLICANT |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
| CofO Issued | 6/8/2025 | DEROLD HAUFF |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/29/2024 | ADRIAN SANCHEZ |
| Address approval | Cleared | 11/2/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Advanced Construction; Lic. No.: 801955-B | 4606 WILLIS AVE #307 SHERMAN OAKS, CA 91403 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/5/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/5/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/14/2025 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 3/27/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 4/2/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 4/2/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 4/2/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/4/2025 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 4/4/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/4/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/4/2025 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 4/4/2025 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 4/4/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 4/4/2025 | Approved | SABAS ALONSO |
| Insulation | 4/7/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 4/10/2025 | Approved | SABAS ALONSO |
| Shower Pan | 4/10/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/16/2025 | Approved | SABAS ALONSO |
| Final | 5/28/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 5/28/2025 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 5/28/2025 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 6/2/2025 | Approved | MICHAEL LEWIS |
| HVAC-Final | 6/2/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 6/2/2025 | Approved | MICHAEL LEWIS |
| Final | 6/4/2025 | Conditional Approval | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 6/4/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 6/4/2025 | Approved | BARRY HACHE |